Operational quality control systems for construction and installation works. Recommendations for the implementation of operational quality control of construction and installation works

Operational (or intermediate) control is carried out at construction sites in the process of performing production operations or construction processes and must ensure the timely identification of defects, the causes of their occurrence and the adoption of measures for their elimination and prevention.

The composition and content of operational control is regulated by the instructions of RSN-73. This knowledge establishes a general procedure for monitoring the implementation of construction and installation and special works during the construction of buildings and structures for various purposes. The task of operational control is to ensure the compliance of the construction, installation and special work performed with the project and the requirements of the regulatory document (SNiP, GOST, OST, etc.), as well as in increasing the responsibility of the performers themselves for the quality of the work performed.

Intermediate control is carried out according to operational control schemes (SOKK).

The operational quality control scheme should contain:

■ a sketch of the structure with an indication of the point of application of control;

■ permissible deviations according to SNiP;

■ main specifications material or structure (strength, frost resistance, fire resistance, etc.);

■ a list of operations, the performance of which must be checked with reference to who exercises this control - foreman, foreman);

■ composition of control;

■ method of control;

■ terms (stages) of carrying out;

■ a list of operations monitored with the participation of a construction laboratory, a geodetic service, as well as specialists of certain types of work. If necessary, indicate operations requiring special tests (systems, assemblies, etc.);

■ list hidden works to be handed over to the customer's technical supervision representative (examples of the design and content of the operational control scheme are given in Appendices 2 and 3) ..

The organization of operational control and verification of its implementation is usually entrusted to the chief engineers of enterprises, who are obliged to provide instructions to the line engineering and technical personnel (before starting work) on the procedure for conducting operational control with a corresponding entry in the facility construction log. Superintendents (foremen) performing operational control of work must fill out special statistical control cards, which reflect the operation performed in violation of regulatory requirements and not accepted from the first presentation. Defects, deviations from the project, GOST, OST during the operational control must be eliminated before the start of subsequent operations.

INSTALLATION OF UNDERGROUND WALL UNITS

03.13.01-87 pp. 3.5, 3.6, tab. 12

Limit deviations:

- from the alignment of the installation guidelines of the wall blocks with the risks of centering axes - no more than 12 mm;

- from the vertical of the top of the planes of the wall blocks -12 mm.

The grade of the solution must correspond to the design one.

The mobility of the bedding solution should be 5-7 cm.

The installation of wall blocks should be carried out in compliance with the dressing.

Not allowed:

The use of a solution, the setting process of which has already begun, as well as the restoration of its plasticity by adding water;

Contamination of the bearing surfaces.

STAGES OF WORK CONTROLLED OPERATIONS CONTROL

(method, volume)

DOCUMENTATION
Preparatory work Verify:

The quality of the surface and appearance of the blocks, the accuracy of their geometric dimensions;

Transfer of the main axes of the foundations to the cast-off;

Preparation of foundation blocks

for installation, including cleaning the supporting surfaces from dirt and ice

Visual Visual,

measuring

Measuring

Visual, every element

Passports for plates and interlocks, general work log
Installation

fundamental

Control:

Installation of foundation blocks, compliance of their position in plan and height with the requirements of the project;

The density of the adhesion of the base of the foundation blocks to the surface of the base;

Grouting the joints cement mortar according to project requirements

Visual

General work log
Acceptance

completed

Verify:

Deviation from the vertical of the planes of the wall blocks;

Deviation of the axes of the foundation blocks relative to the alignment axes;

Grouting joints between blocks

Measuring, each element

Visual

Executive geodetic scheme, acceptance certificate

Control and measuring tool: level, tape measure, metal ruler, plumb line, rule.

Operational control is carried out by a foreman (foreman), a surveyor - in the process of performing work. Acceptance control is carried out by: an employee of the quality service, a foreman (foreman), a representative of the customer's technical supervision.
Requirements for the quality of the structures used

GOST 13580-85 *. Reinforced concrete slabs for strip foundations. Technical conditions. GOST 13579-78 *. Concrete blocks for basement walls. Technical conditions.

Up to 1000 mm - +10 mm;

St. 1000 to 1600 mm - ± 10 mm;

St. 1600 to 3200 mm - ± 15 mm.

Length and width tolerances:

Deviation of the position of the mounting hinge above the plane of the plate + 10 ... -5 mm. Deviations in the position of embedded products:

In the plane of the slab - 10 mm;

From the plane of the slab - 3 mm.

Non-straightness of the upper plane of the slab in any section along the entire length or width:

Up to 1000 mm - 1.5 mm;

Over 1000 to 1600 mm - 3.0 mm;

Over 1600 to 3200 mm - 4.0 mm.

Not allowed:

On the surface of slabs, sinks with a diameter of more than 20 mm or chips of ribs with a depth of more than 20 mm.

Permissible deviations of block sizes:

In length - ± 13 mm;

in width and height - ± 8 mm;

The dimensions of the cutouts are ± 5 mm.

The deviation from the straightness of the profile of the block surfaces should not exceed 3 mm per

the entire length and width of the block.

Not allowed:

- cracks, except for local, superficial, shrinkage cracks with a width of no more than 0.1 mm;

- outcropping of reinforcement, with the exception of outlets.

Work instructions SNiP 3.03.01-87 pp. 3.9,3.11

Installation of foundations is allowed only after the entire complex of earthworks has been completed, the axes have been laid out and the foundation has been installed. Prior to the start of installation, on the upper edges of foundation slabs and blocks and at their bases, risks should be applied with indelible paint, fixing the position of the axes of the slabs and blocks. The supporting surfaces of the slabs and blocks should be cleaned of contamination. The installation of wall blocks should be carried out starting with the installation of lighthouse blocks in the corners of the building and at the intersection of the axes. The lighthouse blocks are installed by combining their axial risks with the risks of the alignment axes in two mutually perpendicular directions. The installation of ordinary blocks should be started after verifying the position of the lighthouse blocks in plan and in height.

Ordinary blocks should be installed, orienting the bottom along the cut of the blocks of the lower row, and the top along the center line. Exterior wall blocks installed below ground level must be aligned to the inner sides e walls, and above - along the outer. Vertical and horizontal joints must be filled with mortar and sewn on both sides.

INSTALLATION OF BALCONY PLATES AND LINKS

Technical requirements

SNiP 3.03.01-87 pp. 3.5, 3.6, tab. 12
Balcony slabs:

The difference between the levels of the plane of the balcony slab and the floor of the room should be no more than 80-1000 mm;

The slope of the balcony slab from outer wall - 2%.

Jumpers:

Permissible deviations of the marks of the supporting surfaces of the wall -10 mm;

The size of the support of the lintels on the walls - according to the project;

The side surface of the lintels should not extend beyond the plane of the wall.

Requirements for the quality of the materials used

GOST 25697-83 *. Slabs of balconies and loggias are reinforced concrete. General technical conditions... GOST 948-84. Reinforced concrete lintels for buildings with brick walls... Technical conditions.

Scope of operations and controls

STAGES OF WORK CONTROLLED OPERATIONS CONTROL

(method, volume)

DOCUMENTATION
Preparatory work Verify:

Availability of a quality document;

Surface quality,

accuracy of geometric parameters, appearance of slabs, lintels;

The presence of markings that determine the design positions of plates and lintels

Visual

Visual, measuring each element

Passports (certificates), general work log
Installation of balcony slabs Control:

Installation of balcony slabs in the design position;

The quality of welding work;

Installation of reinforced concrete lintels in the design position

Measuring, each element

Visual, Measuring Measuring, each element

General

work journal, journal

welding works

Acceptance of completed works Verify:

The actual position of the mounted slabs and lintels;

Quality of welded joints, monolithic joints;

Appearance elements

Measuring Technical inspection Visual Certificate of survey (acceptance) of work performed

Control and measuring tool: metal tape measure, metal ruler, plumb line, level, level.
Operational control is carried out by: foreman (foreman), engineer (laboratory assistant) - in the process of work.
Acceptance control is carried out by: quality service workers, foreman (foreman), representatives of the customer's technical supervision.

DESCRIPTIONS NAME LIMIT
FROM GEOMETRIC parameter geometric parameter DEVIATION, mm
Deviation from linear dimension Product length, mm:
up to 2500 ± 6
St. 2500 to 4000 ± 8
St. 4000 ± 10
Width and Height ± 5
DEVIATION of the position of mortgages Position of embedded parts:
details in plane 3
out of plane 5
Deviation from straightness Straightness of the face surface
by lenght ± 3

Reinforced concrete lintels are allowed to be made with a technological slope of the side and end faces. The dimensions of the lower edge of the web can be less than the corresponding dimensions of the upper edge:

In length - up to 20 mm;

In width - up to 8 mm.

The values ​​of the actual deviations of the geometric parameters of the lintels and balcony slabs should not exceed the limit values ​​indicated in the table.

Grease and rust stains are not allowed on the front surfaces of reinforced concrete products. Markings and signs are applied on the end side of the lintel, and on the balcony slab - on the end side hidden in the wall. The marking must contain:

Product brand;

Short name of the manufacturer;

Date of manufacture;

The value of the mass of the product.

Work instructions

SNiP 3.03.01-87 pp. 2.112, 3.4

Balcony slabs and lintels are installed simultaneously with the erection of the external walls. The supporting parts of the masonry for prefabricated reinforced concrete structures must be made of whole bricks in stitch rows.

When installing balcony slabs, it is necessary to carry out temporary fastenings in the form of supports from a bar. Permanent fixing must be carried out immediately according to the project requirements. Metal embedded parts hidden in masonry must be protected with an anti-corrosion coating.

For welding of fittings, embedded parts and for embedding balcony slabs, certificates of inspection of hidden works should be drawn up.

Technological control consists in checking the compliance of the characteristics, modes and other indicators of the technological process with the established requirements. A kind of technological control is operational control. At operational control product quality is checked for compliance with individual regulatory requirements implemented in the course of the next technological operation. Its purpose is to detect and eliminate defects in the process of manufacturing products or erecting buildings and structures. Operational control is performed by production personnel (workers, foremen, foremen). This type of control is considered to be labor quality control.

During operational control, check:

Hidden parameters of the product, the control of which is subsequently impossible or difficult (reinforcing cages, etc.);

Compliance with the technology for performing construction processes specified in the work production projects;

Compliance of the work performed with working drawings, building codes and regulations for the production of work and standards;

The stability of the parameters of products included in the nomenclature of control of finished products;

Product parameters depending on the quality and condition of technological equipment and technological process (thickness of the concrete cover, location of embedded parts, curvature and non-straightness of the surface).

Operational control is carried out according to special schemes of operational quality control (SOKK) for all construction and installation processes attached to flow charts or workflow charts. SOKK is a project document that defines the performers, composition, method and time of quality control of construction processes for operations. It is developed based on the requirements normative documents and state standards... It lists specific operations and indicates the requirements of the standard (or building codes and regulations) to be followed when performing this operation, and also provides a description of the tool with which the operational control is carried out. The map also indicates who specifically exercises control (worker, foreman, foreman, technical control department, etc.).

Operational control should be carried out after the completion of production operations or construction processes and ensure the timely identification of defects and the reasons for their occurrence, and

timely adoption of measures to eliminate and prevent them.

Operational control should be carried out by work producers and foremen, and self-control by work performers. Operational control should also involve construction laboratories and geodetic services. The main working documents for operational quality control should be operational control schemes developed as part of work production projects.

The operational control scheme should contain:

  1. sketches of structures with an indication of the permissible deviations in dimensions and the required measurement accuracy, as well as information on the required characteristics of the quality of materials;
  2. a list of operations or processes, the quality of which must be checked by the work manufacturer (foreman);
  3. a list of operations or processes controlled with the participation of a construction laboratory and a geodetic service;
  4. a list of hidden works subject to certification with the drawing up of an act;
  5. the requirements of building codes and regulations, and in necessary cases- the main characteristics of the quality of the material (structures);
  6. data on the composition of the control, established on the basis of the requirements of regulatory documents and working drawings, indicating what needs to be checked;
  7. instructions on how to control the operations performed;
  8. the timing of the control.

Operational control is entrusted to foremen and foremen, and its organization to chief engineers of construction and installation organizations.

7. Acceptance control.

Acceptance control finished products are carried out at the final stage of the technological process. The number of parameters checked in this case must meet the requirements of standards and building codes and regulations. Internal inspection control is carried out according to the schedule approved by the management of the enterprise, usually at least once a quarter. Acceptance control should be carried out to check and assess the quality of completed construction enterprises, buildings and structures or their parts, as well as hidden works and individual critical structures. All hidden works are subject to acceptance with the drawing up of acts from the certified one. The certificate of inspection of hidden works should be drawn up for a completed process performed by an independent unit of performers. Drawing up certificates of inspection of hidden work in cases where subsequent work should begin after a long break, should be carried out immediately before the production of subsequent work. Individual critical structures, as soon as they are ready, are subject to acceptance during construction with the preparation of an intermediate acceptance certificate for these structures. The list of critical structures subject to interim acceptance is established by the project.

In addition to production control in construction and installation organizations (input, operational, acceptance) the quality of construction is monitored by state and departmental bodies of control and supervision, acting on the basis of special provisions on them (fire, sanitary, mining, etc.). In construction organizations, organizational, technical and economic measures should be developed to ensure quality control of construction. These events should, in parity, provide for the creation of construction laboratories, geodetic services, advanced training and skills of performers. At all stages of construction, in order to check the effectiveness of previously performed production control, selectively carry out inspection control... It is carried out by special services, if they are part of the construction organization, or commissions specially created for this purpose. According to the results production and inspection quality control Construction and installation works are developing measures to eliminate the identified defects, while taking into account the requirements of the field supervision of design organizations and state supervision bodies.

"Operational control chart" is developed by an enterprise that manufactures, installs or repairs equipment (pipelines) or a specialized design and technological organization and serves to record the results of control of work mainly in the preparation and assembly of parts for welding.

The "Map ..." should reflect the following information:

the name of the enterprise and service performing operational control;

the name of the equipment (pipeline) and designation of the drawing or welding form;

the presence of marking and / or documentation confirming the acceptance of the material (semi-finished product) during the incoming inspection;

cleanliness and absence of damage on the edges and adjacent surfaces of parts;

shape and dimensions of edges, boring (distribution, calibration) of pipe parts;

the presence and type of special methods of preparation and assembly of parts (surfacing on edges and internal surfaces, hemming);

under the condition of bending, the temperature of the metal during this technological operation and the angle of bending are indicated, and under the condition of surfacing - its dimensions, the welding method and the welding materials used, indicating the batch (melt) number and standard, TU or passport;

compliance with the requirements of the PDD for the material, shape and size of backing rings (fusible inserts);

compliance with the PDD of the dimensions of the gaps, displacement of the edges (from the outer and inner sides), fracture of the axes and planes of the parts to be joined in the joint assembled for welding;

the presence of a protective coating on the surfaces of parts (in cases stipulated by the PDD) and the width of the zone of its application;

correct assembly and fastening of parts, dimensions of the assembled unit (the latter - in cases stipulated by the PDD);

date of control, last name, first name and patronymic of the person (persons) who performed operational control and his (their) signatures;

conclusion on the preparation of parts for assembly for welding.

The conclusion on the quality of preparation of parts and assembly of the joint for welding is signed by the head of the preparation and assembly work and the head of the service that carried out the control.

The program of training specialists for certification for the right

performance of work and management of work on visual

and measuring control

I THEORETICAL TRAINING PROGRAM

A. General technical course

Topic 1 Design and installation of equipment for TPP and NPP

1.1 Equipment for thermal and nuclear power plants. Types of thermal and nuclear power plants. The main elements of TPP and their purpose. Physical foundations of nuclear energy. Basic technological schemes of nuclear power plants. Purpose and classification of pipelines and equipment of TPP and NPP. NPP equipment and pipelines groups; categories of welded joints. Categories of pipelines for steam and hot water. Manufacturing, enlargement and installation of pipelines, structures and technological equipment.

1.2 Materials science.

General information about metals, alloys and their properties. Varieties of steels, their characteristics, the concept of micro- and macrostructure, the relationship between the structure and properties of steel. Technological features of various steel grades and their areas of application. Steels and alloys used for the manufacture of thermal mechanical equipment, pipelines and structures for thermal power plants and nuclear power plants. The influence of the physical and mechanical properties of steel (alloy) on the choice of the method of non-destructive testing. Basic concepts of destructive testing methods for metals and alloys; methods of destructive control and their areas of application.

1.3 General information about welding and heat treatment of welded joints.

Welding methods used in the manufacture, installation and repair of equipment and pipelines at TPPs and NPPs. Welding consumables and their fields of application. Heat treatment of welded joints of products and its purpose. Influence of heat treatment on the properties of welded joints. Welded connections. Types of pipelines welded; requirements for structural forms of welded joints. The main zones of the welded joint are: weld metal, fusion zone, heat-affected zone and base metal. Influence of the structural features of the welded joint and the metal of the product on the choice of non-destructive testing methods.

1.4 Types of defects (discontinuities) in welded joints and base metal.

Concept - discontinuity (defect). Classification of defects in welded joints and base metal of products. External (surface) and internal defects. Plane and volumetric defects. Types of defects, causes of their occurrence in welded joints and base metal of products; characteristic types of defects inherent in various welding methods. Defect prevention measures. Influence of defects on the properties and technological strength of the base metal and welded joints. Defect correction methods. Inspection methods, scope of inspection and norms for assessing the quality of fixed sections of welded joints. The number of fixes in the same area.

1.5 Technical requirements for the quality of welded joints and base metal.

General requirements for the quality of the welded joint and the base metal of the product. Incoming quality control of base and welding metals. PDD requirements for control during preparation, assembly, welding (surfacing), heat treatment and when correcting defects. Technical requirements for structural shapes and location of welded joints on the product. Acceptance quality control of welded joints. NTD requirements for the quality of welded joints of TPP and NPP products.

1.6 Basic methods of quality control of welded joints (surfacing) of products.

Methods for control of welded joints (surfacing) and base metal of products by non-destructive (physical) and destructive (laboratory) control methods. Areas of their application and physical entity... Visual and measuring control of welded joints (surfacing) and base metal of products. Non-destructive testing methods: capillary, magnetic particle, ultrasonic, radiographic and tightness (gas and liquid). General information about the destructive methods of testing welded joints. Advantages and disadvantages of non-destructive testing methods. Comprehensive use of methods for monitoring welded joints (surfacing) and base metal of products.

Quality control construction works must be in a special place. That is why the organization of such events requires, first of all, the organization of the labor process at a high level. At the same time, this includes not only the direct participation of persons in the construction of an object, but also logistics, which determines the methods, terms and quality of delivery. necessary materials or finished elements to the construction site. Therefore, simultaneously with the work related to the creation of a new object, actions are being taken to agree and check the quality of the stages already passed.

Operational quality control of construction installation works is part of the activities of supervisory authorities, which are designed to regulate work in the field of creating new capital construction projects. They monitor all types of technical measures for compliance regulatory framework RF. Each type of activity, at a certain stage, provides for specific rules and requirements that must be followed.

Excavation and first inspection

The initial and main works are primarily related to the land plot on which the construction of a new facility or the reconstruction of old buildings is supposed to be carried out. The quality control manual for construction and installation works states that, if necessary, first of all, the soil area must be checked for compliance with the following conditions:

  • Is it necessary to additionally fill up the territory to bring it into a smoother configuration;
  • Whether it is required to create trenches, embankments or excavations to create an enabling environment during construction and in accordance with operational control requirements

In the course of creating new capital construction objects, it must be remembered that it is important for inspection organizations to fix each stage and each action in writing with technical designations. The best option will become a magazine in which all technical documentation and the quality control system will be assessed.

The scheme of operational quality control at this stage is aimed at verifying that citizens or legal entities comply with the correct location of the foundation, the correctness of the selected area for the volume of construction work. This also includes the definition of the use in accordance with the urban planning plan of the land plot and the points established in the building permit.

At this stage of activity, a legal check of the existing documents takes place, as well as a visualized inspection of the territory for compliance with the parameters of the permitted construction and the presence of indents.

Laying the foundation

The most important stage, since it is he who is decisive for subsequent actions. The integrity of the entire object, its service life and the quality of all activities of the construction organization as a whole will depend on the quality of the basis of the real estate object.

The organization of quality control of construction work in this case is aimed at checking the soil layer directly in the place where the foundation will be installed. For this, it is additionally necessary to create a log of the quality of construction and installation works, which will be based on the survey provided by the surveyor. Thus, there should be no debris or objects that could disturb the foundation layer. Also, all work should be carried out under normal weather conditions, no precipitation, or violation of the integrity of the soil and its normal state.

It is important to take into account the quality of structures that are made of either concrete or iron materials, their distance from each other and installation methods. Any violation of the scheme can lead to negative consequences, significantly reduce the life of the building.

The tasks of operational control of the quality of construction work at the time of direct activity on the construction of buildings or structures are:

  • Creation of a certain scheme of operational quality control of applied building materials and mixtures. Visual inspection bricks, blocks, beam elements and floor slabs for their external condition, excluding chips, damage and other shortcomings that prohibit the use of such elements during construction. An indication in the log of shortcomings and measures taken to replace them;
  • Consideration of the operational quality control scheme at the end of the device of the main structures. Thus, a log is kept, which indicates the order of construction and installation of blocks and other systems (floor slabs, beams and columns).

Such tasks are always solved in two stages. Initially, an inspection takes place, and then a check for compliance with the construction project. The entire range of these checks is recorded in the work log and then can serve as the basis for drawing up an act of hidden deficiencies in the implementation of the activities of installation organizations. It is important to remember that any deviations from the standards at this stage will affect the quality of operation in the future. That is why organizations must first of all think about safety, which will guarantee the quality of their work.

Definition of roofing and insulation works

The beginning of repair and installation work occurs when installing insulation systems from water, noise and other negative factors. The construction scheme does not differ from the type of buildings. Therefore, even non-residential premises must be finished in such a way that the rules established by the technical supervision service are fully observed.

If we are talking about the reconstruction of an object, it is necessary to take into account the state of all systems of this structure at the moment. Therefore, in this case, control is reduced to checking the current state of the elements of hydro and noise insulation, and then a plan is developed to strengthen or replace the current systems.

As can be seen from the above, operational control consists of many systems that cannot operate separately from each other. A well-developed scheme and maximum responsibility for the work done is required.

Design and Technological Institute of Industrial Construction

OJSC PKTIpromstroy

OPERATIONAL QUALITY CONTROL CARDS OF BASIC CONSTRUCTION AND INSTALLATION WORKS

1. OPERATIONAL CONTROL CARD WHEN INSTALLING REINFORCED CONCRETE COLUMNS

2. OPERATIONAL CONTROL CHART WHEN INSTALLING LARGE-BLOCK TAPE FOUNDATIONS

3. OPERATIONAL CONTROL CARD WHEN INSTALLING REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS

4. OPERATIONAL CONTROL CARD WHEN MOUNTING THE BARS

5. MAP OF OPERATIONAL CONTROL OF INSTALLATION OF REINFORCED CONCRETE FIRMS AND BEAMS

6. MAP OF OPERATIONAL CONTROL OF INSTALLATION OF COVERING PANELS (COVERINGS)

7. CARD OF OPERATIONAL CONTROL OF WALL FORMWORK INSTALLATION

8. OPERATIONAL CONTROL MAP OF COLUMN AND CEILING FORMWORK INSTALLATION

9. OPERATIONAL CONTROL CARD WHEN INSTALLING THE FOUNDATION FORMWORK

10. KAPTA OF OPERATIONAL CONTROL OF STRUCTURAL REINFORCEMENT

11. MAP OF OPERATIONAL CONTROL OF FLOORS CONCRETE

12. MAP OF OPERATIONAL CONTROL OF WALL CONCRETE

13. MAP OF OPERATIONAL CONTROL OF COLUMN CONCRETE

14. CARD OF OPERATIONAL CONTROL OF PILLAR BRICKS

15. MAP OF OPERATIONAL CONTROL OF BRICK WALLS

16. CARD OF OPERATIONAL CONTROL OF INSTALLATION OF WINDOW AND DOOR BLOCKS

The technological map does not replace the commissioning plan (see SNiP 3.01.01-85 *) The quality of construction and installation works is characterized by the degree of their compliance with the requirements of projects and SNiP. Any deviation from these requirements must be detected and corrected in a timely manner, which can only be achieved by organizing daily operational quality control. Operational quality control of construction and installation works is carried out by the manufacturer of the works and the foreman with the involvement, if necessary, of representatives of the quality management laboratory of the trust (association). The main tasks of operational quality control of construction and installation works: - ensuring the required level of quality of the buildings being erected; - ensuring the implementation of construction and installation works in accordance with the project and the requirements of regulatory documents; - timely identification of the causes of defects in the course of work and taking measures to eliminate them; - increasing the personal responsibility of direct executors and line engineers and technical workers for the quality of the construction and installation work performed. All defects identified in the course of operational control must be eliminated before the start of subsequent operations (works). Operational control must be carried out in strict accordance with the enterprise standard (STP) "Regulation on Operational Quality Control". The main documents of operational quality control are operational control cards. They must constantly be at the construction site with the construction manager and be presented at the request of the persons who control the quality of work. They specify the responsibilities of officials in the implementation of operational control. If the work at the facility is headed by one manager (foreman, foreman), then he performs all the control functions specified in the operational control cards. Operational quality control cards are intended for line engineers and technical workers and foremen, and can also be used by persons exercising control over the quality of construction.

1. OPERATIONAL CONTROL CARD WHEN INSTALLING REINFORCED CONCRETE COLUMNS

Tolerances for the installation of reinforced concrete columns in accordance with the requirements of SNiP 1. The difference in the marks of the top of adjacent columns or support sites (brackets, consoles) ± 10mm 2. The difference in the marks of the top of the columns or support sites within the area to be verified: with contact installation 12 + 2, where - the ordinal number of the tier when installed by beacons 10 mm 3. Displacement of the axes of the columns of single-storey buildings in the upper section from the vertical at the height of the columns H: in meters up to 10 m ± 10 mm over 10 m 0.001 N, but not more than 35 mm 4. Displacement of the axes of the columns multi-storey buildings in the upper section relative to the alignment axes for columns with a height: up to 4.5 m ± 10 mm over 4.6 m ± 15 im

Table 1

Operations subject to control

Control composition

Control method

Control time

Work

Works to be activated

Work Producer

Preparatory work

Correct storage

Visually

Before installation

Marking the bottom of the foundation glass

Using a level

Before installation

Surveyor

Column installation

Reliability of slinging, verticality of installation, alignment; reference pads marks; temporary attachment

Visually; using a level; with theodolite

During installation

Surveyor

Welding metal parts

Quality of welded seams

Visually

During installation

Corrosion protection of metal parts

Visually

During installation

If necessary, the laboratory

Monolithing of columns

Thoroughness of monolithing

Visually

During installation

Preparatory work (acceptance of structures)

Availability of passports, drawings, geometrical dimensions, external defects, drawing of alignment axes, marks, dimensions of support areas, correct location of embedded parts

Visually; with a steel meter

Before installation

Column site preparation

Cleaning of glasses, dimensions of the foundation glass; the presence of scratches on the foundation

Before installation

Installing the mounting hardware

Fixing precision

Visually

During installation

Welding metal parts

Compliance with the project; welding of electrodes; seam sizes

Visually

During installation

Laboratory

Cementing columns in foundations

Grade, consistency of concrete mix, thoroughness of compaction

Visually, using a standard cone

During installation

Laboratory

2. OPERATIONAL CONTROL CHART WHEN INSTALLING LARGE-BLOCK TAPE FOUNDATIONS

Tolerances for the installation of large-block strip foundations in accordance with the requirements of SNiP III -16-73 1. Offset of the axes of foundation blocks and foundation wall blocks relative to the centerline axes ± 10 mm 2. Deviation of the marks of the upper supporting surfaces of foundation elements - 10 mm 3. Offset of axes or edges of wall blocks in the lower section relative to the center axes or geometric axes of the structures below them ± 5mm

table 2

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Determination of the state of soils

Visually

Before installation

The correct location of the pit relative to the center drawing, the reliability of fastening, the mark of the bottom of the pit

Visually, using a level and tape measure

Before installation

Surveyor

Sand or gravel top mark

Using a level

Before installation

Surveyor

Correct storage

Visually

Before installation

Stake out foundation axes

Accuracy of determining the position of the corners of the building. Compliance with the project of the distances between the axes of prefabricated foundations

With theodolite and tape measure

Before installation

Surveyor

Installation of foundation blocks

Visually

During installation

Precision of installation, foundation blocks. Support and abutment density

Using a level and a plumb line

During installation

Compliance with the design

Using a level

After installing blocks

Surveyor

Preparatory work

Sufficiency of the size of the pits

With a tape measure

Before installation

The thickness of the sand or gravel pad, the quality of its compaction

Visually, using a steel meter

Before installation

Cleaning foundation blocks from dirt, from snow in winter

Visually

Before installation

Availability of passports for reinforced concrete structures; compliance of the geometric dimensions of the blocks with the project; external defects

Roulette

Before installation

Stake out the foundation axes

The correct tension of the axles, the accuracy of the intersection of the axes on the foundation blocks

With theodolite

Before installation

Surveyor

Installation of foundation blocks

Compliance with installation technology, Technological map

Visually

During installation

3. OPERATIONAL CONTROL CARD WHEN INSTALLING REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS

Tolerances for the installation of reinforced concrete foundations for columns in accordance with the requirements of SNiP III -16-73 1. Displacement of the axes of the foundation glasses relative to the centerline axes ± 10mm 2. The deviation of the marks of the upper supporting surfaces of the foundation elements - 10mm 3. The deviation of the marks of the bottom of the foundation glasses - 20mm

Table 3

Operations subject to control

Control composition

Control method

Control time

Works to be activated

Work Producer

Preparatory work

Preparation of the base for foundations, its condition, dimensions, marks, protection against freezing in winter

Using a level, steel meter, tape measure

Before installation

Surveyor

The dimensions of the pits, the correctness of their location and the reliability of fastening the walls of the pit, marks of the bottom of the pit

Visually, using a level, tape measure, plumb line

Before installation

Base top mark and cushion horizontal

Using a level

Before installation

Surveyor

Side waterproofing of foundation blocks

Insulation quality

Visually

After installation

Preparatory work

Sand or gravel pad thickness and compaction quality

Visually i with a steel meter

Before installation

Cleaning from dirt, from snow and ice in winter

Visually

Before installation

Checking the geometric dimensions of blocks, defects. Comparison of passport data of reinforced concrete structures with design

Before installation

Installation of control lines along the axes of the foundations

Compliance with the project of the axes transferred to the bottom of the excavation.

Accuracy of the position of the top of the control line

With theodolite, level

Before installation

Installation and alignment of blocks

Installation accuracy, compliance with design marks and axes

With the help of a level, relative

During installation

Surveyor

4. OPERATIONAL CONTROL CARD WHEN MOUNTING THE BARS

Tolerances for the installation of girders in accordance with the requirements of SNiP III -16-73 1. Displacement of the girder axes along the lower chord relative to the geometric axes of the supporting structures ± 6 mm 2. Deviation of the distances between the axes of the girders at the level of the upper chords ± 20mm 3. The tolerances of the support areas and the tolerances of the gaps between the elements are determined by the project

Table 4

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Correct storage of structures

Visually

Before installation

Aligning support surfaces on columns

Compliance of the elevations of the support pads of the columns with the design ones, the correctness of the application of the alignment axes

With theodolite, level, steel meter

Before installation

Surveyor

Installation of crossbars

Correct and reliable slinging

Visually

During installation

Alignment of the girder axes with the alignment axes on the supporting structures, verticality and density of the girder support

Visually, using a plumb line

During installation

Welding of embedded parts in the joints

Visually, using a steel meter

During installation

If necessary, the laboratory

Cementing joints

The appearance of the joints, the strength of concrete at the joint

Visually using a reference hammer

After stripping the joint

Laboratory

Preparatory work

Compliance of geometric dimensions with design ones, external defects, availability of passports, correct location of embedded parts, cleaning them

Visually, using a steel meter, tape measure

Before installation

Aligning support surfaces on columns

Visually, using a steel meter

Installation of crossbars

Correctness of drawing axial and control marks on the crossbars

Visually, using a steel meter, tape measure

During installation

Visually

During installation

Compliance with the design of the joint and the brand of electrodes according to the project

Visually

During installation

Cementing joints

Density and strength of formwork

Visually

During installation

Concrete grade

Before concreting

Laboratory

Joint sealing quality

Visually

In the process of concreting

Joint filling quality

Visually

After stripping

5. MAP OF OPERATIONAL CONTROL OF INSTALLATION OF REINFORCED CONCRETE FIRMS AND BEAMS

Tolerances for the installation of reinforced concrete trusses and beams in accordance with the requirements of SNiP III -16-73 1. Displacement of the axes of the trusses (beams) along the lower chord relative to the geometric axes of the supporting structures ± 5mm 2. Deviation of the distances between the axes of the trusses (beams) at the level of the upper chords ± 20 mm 3. The tolerances of the support areas and the tolerances of the gaps between the elements are determined by the project

Table 5

Quality Control Persons

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Correct storage of reinforced concrete structures

Visually

Before installation

Alignment of supporting surfaces of previously mounted structures

Compliance of the elevations of the reference pads with the design ones, the correctness of the application of the stake out axes

Before installation

Surveyor

Installation of trusses, beams

Correct and reliable slinging

Visually

During installation

Alignment of axes of beams trusses with alignment axes, verticality of support structures

Visually, using a plumb line

During installation

Reliability of temporary fastening

Visually

During installation

Welding of embedded parts in the joints

Welding quality, acceptance certificates for welded joints, weld dimensions

Visually, using a steel meter

During the installation process

Anti-corrosion protection

The quality of the application of the anti-corrosion layer

Visually

Before monolithic

If necessary, the laboratory

Preparatory work

Availability of passports, geometric dimensions, external defects, reinforced concrete structures

Visually, using a steel meter

Before installation

Arrangement of embedded parts, cleaning them from rust and concrete build-up

Visually, using a steel meter

Before installation

Alignment of supporting surfaces of structures

Position of support pads and embedded parts

Visually

Before installation

Installation of trusses of beams

The presence and correctness of drawing axial and control marks on structures

With a steel meter

During installation

Correctness of installation technology

Visually

During installation

Welding of embedded parts in the joints

Type of electrodes, conformity of the joint to the project

Visually

During installation

Cementing joints

Density and strength of formwork

Visually

Before concreting

Concrete grade, compaction quality

Visually

In the process of monolithing

Laboratory

Joint appearance, quality of sealing

Visually

In the process of monolithing

Compliance of the elevations of the installed structures with the design ones, the distance between the axes

Visually

After installation

Surveyor

6. MAP OF OPERATIONAL CONTROL OF INSTALLATION OF COVERING PANELS (COVERINGS)

Tolerances for the installation of floor panels (coverings) in accordance with the requirements of SNiP III -16-73 1. The difference in the marks of the front surfaces of two adjacent floor slabs (coverings) at the joint is ± 5 mm 2. The displacement in plan of the cover plates or floors relative to their design position by support surfaces and nodes of trusses and other supporting structures (along the supporting sides of the slabs), not allowed 3. Permissible deviations in the dimensions of the support areas and gaps between structural elements are determined by the project

Table 6

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons attracted with control

Works to be activated

Work Producer

Preparatory work

Correct storage of panels

Visually

Before installation

Compliance of elevations and support areas with the design

Using a level, tape measure, steel meter

Before installation

Surveyor

Installation of floor panels

Instrumental check of the mounting horizon of each floor

Using a level

During installation

Surveyor

Corrosion protection of anchors

Anti-corrosion coating quality

Visually

Securing joints

Laboratory

Cementing joints

The quality of the monolithing of the joints

Visually

After monolithing

Preparatory work

Availability of passports, geometric changes, surface quality of structures

Before installation

Correct location of embedded parts, mounting loops

Visually, using a tape measure, a steel meter

Before installation

Implementation of the support row of brickwork with pokes

Visually

Before installation

Making a bed from a solution

Compliance with the grade of the mortar to the project, the thickness of the mortar layer

Visually

During installation

Laboratory

Panel mounting

Compliance with the support area, the position of the panel in the plan, the density of abutment to the supporting surface, the correct installation technology

Visually

During installation

Anchoring panels

Compliance of anchoring with project requirements

Visually

Before monolithic

Cementing joints

Cleaning and moistening of the abutting surfaces, compliance of the grade of solution or concrete with the design

In the process of monolithing

Laboratory

7. CARD OF OPERATIONAL CONTROL OF WALL FORMWORK INSTALLATION

Tolerances when installing wall formwork in accordance with the requirements of SNiP III -15-76 1. Distance from the vertical or design slope of the planes of wall formwork and their intersection lines with a wall height of up to 5m 10 mm with a wall height of more than 5m 15 mm 2. Offset of the axes of the wall formwork : from the design position 8 mm 3. Internal dimensions of the wall formwork from the design dimensions 3 mm 4. Local irregularities in the formwork when checking with a 2-meter rail 3 mm

Table 7

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Visually

Before installing the formwork

Formwork installation

After installing the wall formwork (before fixing it)

Surveyor

Accuracy of installation of embedded parts, their fastening

With a meter, tape measure

After installing the formwork

Preparatory work

Compliance with the project and quality of formwork panels, correct storage

Visually, using a meter

Before installing the formwork

Formwork installation

Compliance with design dimensions, verticality

Using a meter, a plumb line

During the installation of the formwork

The quality of the formwork fasteners

Visually

During the installation of the formwork

The quality of the inner surface of the formwork

During the installation of the formwork

8. OPERATIONAL CONTROL MAP OF COLUMN AND CEILING FORMWORK INSTALLATION

Tolerances for the installation of the formwork of columns and ceilings in accordance with the requirements of SNiP III -15-76 1. The distance between the supports of the bending formwork elements and the distance between the ties of the vertical supporting structures from the design dimensions: for 1 m length of 25 mm for the entire span of at least 75 mm 2. Distance from the vertical or the design slope of the planes of the formwork and the lines of their intersection: for 1 m of height 5 mm for the entire height of columns up to 5 m 10 mm - "- more than 5 m 15 mm for the entire height of beams 5 mm 3. Displacement of the axes of the formwork from the design position of the columns 8 mm - "- beams 10 mm 4. The distance between the inner surfaces of the formwork of columns, beams from the design dimensions - 3 mm 5. Local irregularities of the formwork when checking with a 2-meter rail - 3 mm

Table 8

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Determination of the state of the base (for columns)

Visually

Before installing the formwork

Formwork installation

The suitability of the supporting scaffolds and scaffolds to the project, their stability and rigidity

Visually, using a steel meter, tape measure, plumb line

Before installing the formwork

Correspondence of the position of the formwork to the installation axes

Using theodolite, plumb line, tape measure

During the installation of the formwork

Surveyor

Accuracy of installation of embedded parts

With a steel meter, tape measure

Formwork ambassador

Preparatory work

Quality of formwork panels and fasteners

Visually, using a steel meter

Before installing the formwork

Correct storage of formwork elements

Visually

Before installing the formwork

Formwork installation

Compliance with design dimensions and marks

Using a level, plumb line, level, steel meter, tape measure

During the installation of the formwork

The surface quality of the formwork (density in the conjugation of the boards)

Visually, using a 2-meter rail

During the installation of the formwork

Formwork fastening quality

Visually

During the installation of the formwork

9. OPERATIONAL CONTROL CARD WHEN INSTALLING THE FOUNDATION FORMWORK

Tolerances for the installation of formwork foundations in accordance with the requirements of SNiP III -15-76 1. Distance from the vertical or the design position of the planes of the formwork foundations and their intersection lines at 1m height 5mm 2. Displacement of the foundation formwork axes from the design position of 15mm foundations for steel structures , (L is the length of the span or the step of the structure, m) 3. Local unevenness of the formwork (when checking with a 2 m long rail) 3 mm

Table 9

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Determination of the condition of the foundation

Visually

Before installing the formwork

Formwork installation

Correspondence of the position of the formwork to the installation axes, the accuracy of the installation of embedded parts and their fastening

Using theodolite, tape measure, plumb line, steel meter

After installing the formwork

Surveyor

Preparatory work

Compliance with the project and the quality of formwork panels, blocks and fasteners, correct storage of formwork elements

Visually, using a steel meter

Before installing the formwork

Formwork installation

Compliance with design dimensions and marks. The horizontality and verticality of the formwork elements, the quality of the fasteners, the quality of the inner surface of the formwork

Visually, using a level, plumb line, steel meter

During the installation of the formwork

10. KAPTA OF OPERATIONAL CONTROL OF STRUCTURAL REINFORCEMENT

Tolerances for the reinforcement of structures in accordance with the requirements of SNiP III -15-76 1. Reinforcing steel supplied to the construction must undergo an external examination upon acceptance. measurements and control tests in cases stipulated in the project 2. Replacement of the reinforcing steel provided for by the project is agreed with the design organization 3. Before the installation of the reinforcement, the formwork is checked, the shims are fastened, providing a gap for the protective layer equipment 4. The assembled reinforcement is secured from displacement and protected from damage during concreting 5. The displacement of reinforcing bars when they are installed in the formwork should not exceed 1/5 of the largest diameter of the bar and 1/4 of the diameter of the bar to be installed 6. It is prohibited to use spacers to form a protective layer from rebar scraps, wooden bars and crushed stone
Table 10

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Reinforcement acceptance

Compliance of reinforcing meshes and cages to the project (passport)

Visually

Before installation

Installation of fittings

Installation of grids, frames, embedded parts in accordance with the project

With a plumb line, steel meter

During installation

Providing a protective layer

With a steel meter

When installing the formwork

Securing joints, frames, meshes (welding, knitting)

Visually

After fixing

Laboratory

Acceptance fittings

Selectively Checks the diameter of the reinforcement, the distance between the working bars in meshes and frames

Using a caliper and a steel meter

Before installation

Position of embedded parts

With a steel meter

Before installation

Quality of execution of reinforcement attachment points in the mesh frame

Visually

Before installation

Reinforcement storage

Correctness of warehousing and storage

Visually

Before installation

Correct sling

Visually, using a steel meter

During the installation of fittings

Installation of fittings

Compliance with the technology adopted in technological map or Poland

Visually

During the installation of fittings

Correctness of the layout of the grids, the correct fastening of the reinforcement in the formwork

Visually, using a steel meter

During the installation of fittings

Correct installation of running boards on the slab

Visually

During the installation of fittings

11. MAP OF OPERATIONAL CONTROL OF FLOORS CONCRETE

Tolerances when concreting floors in accordance with the requirements of SNiP III -15-76 1. Local deviations of the concrete surface from the design when checking structures with a rail 2 m ± 5 mm long 2. In the marks of surfaces and embedded parts that serve as supports for metal or prefabricated reinforced concrete elements ± 5 mm 3. In the location of the anchor bolts, in plan inside the contour of the support - 5 mm in the plan outside the contour of the support - 10 mm 4. The difference in height marks at the junction of two adjacent surfaces - 3mm

Table 11

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Formwork quality

Visually

Before concreting

Condition of fittings and embedded parts, certificate of acceptance of fittings

Visually

Before concreting

Stripping

Surface quality, compliance with the design of holes, geometric dimensions

Visually, using a meter

After stripping

Concrete strength, homogeneity, cracks

Visually, ultrasonic instrument

After stripping

Laboratory

Preparatory work

Substrate quality, removal of the top layer at working seams, notching, rinsing

Visually

Before concreting

Laying concrete mix

Concrete mix quality

With the help of the StroyTSNIIL cone, press

Before concreting

Laboratory

Visually

In the process of laying

Visually

In the process of laying

Outdoor temperature

With a thermometer

In the process of laying

Concrete compaction

Permutation step and immersion depth of vibrators

Visually

In the process of compaction

Adequate vibration and concrete thickness during compaction

Visually

In the process of compaction

Concrete care during hardening

With a thermometer

During hardening

12. MAP OF OPERATIONAL CONTROL OF WALL CONCRETE

Tolerances when concreting walls in accordance with the requirements of SNiP III -15-76 1. Planes and lines of their intersection from the vertical or the design slope to the entire height: walls supporting monolithic coverings and ceilings ± 15mm walls supporting prefabricated joist structures ± 10mm 2. Horizontal planes on the whole plane of the area to be verified ± 20mm 3. Local deviations of the concrete surface from the design when checking the structure with a rail 2 m long ± 5 mm 4. In the marks of surfaces and embedded parts - 5 mm

Table 12

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Formwork quality

Visually

Before concreting

Compliance with the base elevation design

Using a level

Before concreting

Surveyor

Condition of fittings and embedded parts, certificate of acceptance of fittings

Visually

Before concreting

Stripping

Surface quality, compliance with the design of holes, openings, channels, geometric dimensions

Visually, using a steel meter

After stripping

The strength of concrete, its homogeneity, the presence of supports, cracks

With an ultrasonic device, visually

After stripping

Laboratory

Preparatory work

The quality of the base, the removal of the top layer at the working seams, the notch, the groove, the presence of waterproofing

Visually

Before concreting

Laying concrete mix

Concrete mix quality (mobility, cube strength)

Before concreting

Laboratory

The correctness of the technology for placing the concrete mixture

Visually

In the process of laying

Correctness of working seams

Visually

In the process of laying

Outside air and concrete temperature (winter)

With a thermometer

In the process of laying

Concrete compaction

Permutation step and immersion depth of vibrators

Visually, using a steel meter

In the process of compaction

Adequate vibration and concrete layer thickness when laying

Visually, using a steel meter

In the process of compaction

Compliance with humidity and temperature regimes

With a thermometer

During hardening

13. MAP OF OPERATIONAL CONTROL OF COLUMN CONCRETE

Concreting tolerances in accordance with the requirements of SNiP III -15-76 1. Planes and lines of their intersection from the vertical or from the design slope to the entire height of the columns supporting monolithic coverings and floors ± 15 mm As above for columns supporting prefabricated girders ± 10 mm 2. Horizontal planes on the entire plane of the area to be verified ± 20 mm 3. Local deviations of the concrete surface from the design when checking structures with a 2 m long rail, except for supporting surfaces ± 6 mm 4. In the dimensions of the cross-section of elements + 6 mm - 3 mm 5. In the marks of surfaces and embedded parts that serve as supports for metal or prefabricated reinforced concrete elements - 5 mm

Table 13

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons or subdivisions involved in control

Works to be activated

Work Producer

Preparatory work

Formwork quality

Visually

Before concreting

Compliance with the base elevation design

Using a level

Before concreting

Surveyor

Condition of fittings, embedded parts, certificate of acceptance of fittings

Visually

Before concreting

Stripping

Determination of the surface quality, compliance with the project of geometric dimensions, the correct location of embedded parts, marks of the top of the columns

Visually, using a steel meter, level

After stripping

Surveyor

Determination of the strength of concrete, its homogeneity

Using ultrasonic devices

After stripping

Laboratory

Preparatory work

Determination of the quality of the base (cleaning from dirt, ice, snow, etc.)

Visually

Before concreting

Laying concrete mix

Determination of the quality of the concrete mix (mobility, cube strength)

With the help of the StroyTSNIIL cone, press (PSU-500)

Before installation into the structure

Laboratory

Compliance with the technology of concrete placement

Visually

In the process of laying

Concrete compaction

Temperature control of the outside air and concrete mix (in winter)

With a thermometer

In the process of laying

Compliance with the step of permutation and the immersion depth of the vibrators, the correctness of their installation

Visually, using a steel meter

In the process of compaction

Determination of the sufficiency of vibration and the thickness of the concrete layer

Visually, using a steel meter

In the process of compaction

Care concrete mix when hardening

Compliance with humidity and temperature conditions

With a thermometer

During hardening

Laboratory

14. CARD OF OPERATIONAL CONTROL OF PILLAR BRICKS

Tolerances for brickwork of pillars in accordance with the requirements of SNiP III -17-78 1. Deviations from the design dimensions: 10mm in thickness along the marks of cutoffs and floors 10mm in offset of the axes of structures 10mm 2. Deviation of surfaces and masonry angles from the vertical: 10mm per floor for the whole building 30mm 3. Irregularities on the vertical surface of the masonry, detected when applying a strip with a length of 2m 5mm

Table 14

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Correctness of anchoring of pillars to alignment axes

Visually, using a plumb line

Before laying

Brickwork pillars

Determining the correctness of the masonry technology and dressing the seams

Using a plumb line, steel meter, visually

In the process of laying

Determination of the conformity of the actual position of the performed brick pillars the project, the alignment of the pillars of different floors

Visually, using a plumb line, a steel meter

In the process of laying

Marking cutoffs of brickwork and floors, the correctness of the cushion under the beams, the support of the beams on the cushions and their embedding in the masonry

Visually, using a level, steel meter

After installing the pillow and installing the beam

Surveyor

Preparatory work

Determination of the base for the pillars, the presence of waterproofing

Visually

Before the start of laying the pillars

Determination of the quality of bricks, fittings, embedded parts

Visually, measuring, checking passports and certificates

Before the start of laying the pillars

Laboratory

Brickwork pillars

Sizing, filling and dressing of seams;

With a steel meter

After completing every 5m of masonry

The geometric dimensions of the cross-section of the pillars

With a steel meter

In the process of masonry

Verticality of masonry, irregularities on the surface

Using a plumb line, rail, steel meter

After the end of the laying of the pillar to the height of the floor

Reinforcement of masonry

Correct position of reinforcement, distance between grids along the height of the column, diameter of rebars and distance between them

Using a steel meter, caliper

As the reinforcement is laid

15. MAP OF OPERATIONAL CONTROL OF BRICK WALLS

Tolerances for masonry walls in accordance with the requirements of SNiP III -17-78 1. Deviation from the design dimensions; by thickness 15 mm by marks of cutoffs and floors 10 mm by width of walls 15 mm by width of openings 15 mm by offset of adjacent axes window openings 20 mm by displacement of the axes of structures 10 mm 2. Deviations of surfaces and masonry angles from the vertical: for one floor 10 mm for the whole building 30 mm 3. Deviations of rows of masonry from the horizontal by 10 m length 15 mm 4. Irregularities on the vertical surface of the masonry, detected when overlaying a 2-meter rail 10 mm

Table 15

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Brickwork walls.

The quality of bricks, mortar, fittings, embedded parts

External examination, measurement, verification of passports and certificates

Before laying the walls of the floor

In case of doubt, the laboratory

Axis layout is correct

With a steel tape measure, meter

Before laying

Horizontal marks of cutoffs of masonry for overlapping

With the help of a level, staff.level

Before installing floor panels

Surveyor

Alignment of ventilation ducts and sealing of ventilation units

Visually, using a plumb line

After finishing laying the walls of the floor

Reinforcement of masonry

Correct positioning of reinforcement, diameter of bars, etc.

Visually, using a steel meter

Before installing the fittings

Installation of prefabricated reinforced concrete slabs overlap

Supporting ceilings on groans, embedding, anchoring

Visually, using a steel meter

After installing the floor

Anti-corrosion coating of embedded parts

Thickness, density and adhesion of the coating

Visually, using a thickness gauge, an engraving graver

Before sealing

Laboratory

Installation of balconies

Embedding, elevation, slope of balconies

With a steel meter, level, 2 meter rail

After installing balconies

Masonry walls

Geometric dimensions of the masonry

With a steel tape measure, meter

Verticality, horizontality and masonry surface

Using a level, rail, plumb line

During and after the end of the masonry of the walls of the floor

Quality of masonry joints

With a steel meter, 2 meter rail

After every 10m 3 masonry has been completed

Stakeout and bottom elevations of openings

Using a steel tape measure. level, level

Before laying the walls

Removal of the mark + 1m from the finished floor

Using a level

After finishing the masonry of the floor

Layout of apartments

Visually

After the start of laying the walls

Geometric dimensions of the premises

Using a steel tape measure

After the start of laying the walls

Jumper setting

Jumper position, support, placement, termination

Visually, using a steel meter

After installing the jumpers

Installation staircases

Position of pistillate pads, support, placement, embedding

Visually, using a steel meter

After installing sites

Welding of embedded parts

Length, height, quality of welds

Visually, by tapping with a hammer

Before anti-corrosion coating

Soundproofing device

Construction, workmanship

Visually

Immediately after finishing work

16. CARD OF OPERATIONAL CONTROL OF INSTALLATION OF WINDOW AND DOOR BLOCKS

Rules for installing window and door blocks in accordance with the requirements of SNiP III -19-76 1. Surfaces of window and door blocks adjacent to stone walls, antiseptic with waterproofing materials 2. The gaps between the box and the masonry of the outer walls are sealed with thermal insulation materials 3. Window and door frames in stone walls and partitions, they are fastened with screws or steel ruffs driven into wood antiseptic corks. Each vertical block of the box is fixed in at least 2 places, the distance between them does not exceed 1 meter
Table 16

Quality Control Persons

Operations subject to control

Control composition

Control method

Control time

Persons involved in control

Works to be activated

Work Producer

Preparatory work

Appearance, factory readiness, compliance with standards, ENiP and the project, completeness of delivery of window and door blocks, availability of acts of antiseptic treatment

Visually

When accepting blocks

Presence of antiseptic plugs for fixing blocks

Visually

Before installing blocks

Transportation and storage conditions

Visually

At the construction site

Installation of door and window blocks

Correctness of installation at a given elevation and along a given axis

Using a level, plumb line, tape measure

After installing the boxes

Fastening boxes

Visually

After installing the boxes

Density of fit of window and door sashes

Visually

After installing the boxes

Waterproofing of junction points between blocks and masonry

Visually

After installation

Caulking with heat-insulating material with sealing compound. Coating with a solution of the joints of blocks with masonry

Visually

After installing the box

The gap between the floor surface and the door leaf

With a steel meter

After installing the box

Installation of window sill boards

The presence of teardrops in wooden window sill boards

Visually

Before installing the window sill boards

Antiseptic and insulation of the bottom board of the surface of wooden window sills

Visually

Before installing the window sill boards

The slope of the sill board

With a rail, level, steel meter

After installing the window sill boards

Platband wall overlap

With the help of the steel subway

Did you like the article? Share it
To the top