Technical card for the installation of the channel formwork. Technological map for the installation of the formwork of a monolithic house

The installation of the formwork is carried out using a KB 403 tower crane with a boom length of 30 m, installed according to the construction plan. The installation of the formwork should be carried out according to the grips. Each floor is divided into two sections in the plan.

Columns, walls and ceilings are to be concreted in the "Peri" formwork. The formwork kit consists of:

STEN - made of metal panels lined with water-resistant plywood 21 mm thick, withstanding the pressure of freshly laid concrete of 60 kN / m 2; straightening locks BFD, providing in one operation the connectivity, evenness and density of the formwork panels; strands DV - 15 with a nut - gasket with a permissible load on the strand of 90 kN; leveling tie rod PCC with a support, ensuring the stability of the formwork structures and designed for a load of 30 kN; consoles of suspended scaffolding TRZh 120, ensuring safety when the load on the platform is 150 kg / m 2.

COLUMN - metal panels TRS, lined with waterproof plywood 21 mm thick, withstanding the permissible pressure of freshly laid concrete of 100 kN / m 2, column tension bolts with a permissible bolt load of 90 kN.

COVERINGS - from lattice beams GT 24 different lengths with a bearing capacity - transverse force in struts - 14 kN, bending moment - 7 kNm, PER 30 supports with a bearing capacity of 30 kN; panels made of waterproof plywood 21 mm thick.

The formwork is delivered to the construction site in special containers by road and stored under a canopy.

See below for the formwork installation scheme, it shows the arrangement of work tables and installation and docking of PERI carts.

Before starting the installation of the formwork on the grip, it is necessary to perform:

Concrete reinforced concrete slab with reinforcement outlets for columns, walls, elevator shaft;

Apply centerline risks to reinforced concrete slabs;

Apply the concrete-release liquid "Pera-Wedge" to the formwork panels using a spray gun;

installation of design fittings;

delivery of tools, devices and equipment to the workplace.

Formwork installation scheme.

The sequence of formwork installation at the grip:

WALLS and COLUMNS:

Install the block of outer formwork panels on the spacers;

Install fittings;

Install the block of internal panels on straps and locks with scaffolding and flooring consoles hanging.

The transfer of the main axes of the building to the slab is carried out from the benchmarks. All other building axes are set out from the main axes of the measurement paths. Control over the erection of a monolithic house vertically is carried out floor by floor by theodolites using the oblique design method.

When performing geodetic works, it is necessary to be guided by SNiP 3.01.03 - 84 "Geodetic works in construction".

To reduce the grip of the deck with concrete surface clean it thoroughly and spray it with Peri-Klin concrete release fluid. Clean immediately after removing the formwork by spraying with water, then with a rubber-tipped scraper and a hair brush and spraying with concrete release agent. Apply the concrete release fluid with a hand-held spray gun. Apply at the storage site (in winter - in a warm room). Provide measures to prevent the lubricating film from being washed off by rain.

Slinging of the formwork is carried out using a special TRIO hook included in the formwork kit and a transport sling with four ropes. To lift the panels, use two TRIO crane hooks (load-bearing capacity of one hook - 1.5 t).

See below for the slinging scheme of formwork elements.

The lifting of small and piece elements should be carried out in containers.

Slinging scheme of formwork elements.

The sequence of operations during the installation of wall formwork:

The position of the diaphragm is marked on the spot, using perforators, holes Ø = 25 mm with a depth of 90 mm are drilled in reinforced concrete slabs for the installation of NKD-S M 20 anchors.

On the stand, in a horizontal position, a package of shields (3 pcs.) Is assembled, connected with BFP locks with RSS1 spacers hinged on them.

With the help of crane hooks of the "Peri" system (2 pcs. Per transport unit), the package of shields is lifted to a vertical position and transported by a crane to the installation site.

The package of shields is installed according to the risks in the design position on the outer section of the diaphragm and is fastened with RSS1 spacers with NKD-S M20 anchors to reinforced concrete slab... Separate panels or panels are docked to the installed formwork, depending on the length of the diaphragm, and fastened together with BFD locks in the amount specified in the project.

The entire structure is brought to a vertical position with the help of RSS1 struts, and then reinforcement work is started.

After the completion of the reinforcement work, the inner row of formwork panels is mounted, connected to the previously installed panels using DW-15 straps and washer nuts, with the installation of PVC-U pipes Ø = 25 mm in length to the thickness of the diaphragm.

Then end shields Shch-1 are installed, connected to the formwork shields with BFD locks and TAR-85 leveling locks, scaffolding brackets TRG - 120 and wooden flooring 35 - 40 mm thick are hung.

The entire structure is finally brought to a strictly vertical position and is handed over for concrete work.

COLUMNS:

Reinforcement work is in progress.

On a horizontal stand, a formwork block is assembled from two panels connected by column bolts.

By means of a crane equipped with two-hook TRIO slings, the unit is lifted to a vertical position and placed on a horizontal platform and temporarily fixed to the base using a spacer RSS1.

The third shield is being mounted.

The block of three panels is transported to the installation site using a tower crane with two TRIO hooks and is mounted in the design position, with the RSS1 spacer fastening to the floor slab.

The fourth panel is mounted and secured by the RSS1 spacer.

The scaffolding consoles are hung, and the scaffolding panel boarding is performed.

The formwork is brought into a strictly vertical position using the RSS1 spacers. The formwork is ready for concreting the elevator shaft.

The internal elevator shafts are marked on the foundation slab.

On the stand, in a horizontal position, four packages of panels are assembled to the length of the inner wall of the elevator shaft with fastening to each other with BFD locks according to the project.

With the help of crane hooks of the TRIO system (2 pcs. Per transport unit), the package is lifted to a vertical position and transported to the installation site by a tower crane. The package is installed in the design position with temporary fastening of the RSST brace to the reinforced concrete slab. Then the rest of the panels are installed and connected with BFD locks according to the project.

Reinforcement works are in progress.

After the completion of the reinforcement work, the external formwork panels of the elevator shaft are installed, connected to the previously installed formwork with DW 15 ties with washer nuts and PVC-U pipes Ø 25 mm long by the thickness of the elevator wall, leveling locks TAR - 85 and between themselves with BFD locks according to the project.

The braces RSS1 are installed, the scaffolds TRG-120 are suspended and the boardwalk is made according to the project.

With the help of RSS1 struts, the structure is brought into a vertical position and handed over for concrete work.

Concrete work is in progress.

Sequence of installation of the elevator shaft formwork from elevation +0.000

Support elements (stand-stop) are installed in the upper holes, freed from the straps, to support the next tier of the formwork according to the project.

The device of the flooring in the elevator shaft and in the staircase for the production of installation and reinforcement works is being carried out.

The internal formwork of the elevator shaft (assembled) is mounted using a tower crane on the installed supporting elements (stop-posts) in the elevator shaft.

Reinforcement work is being carried out on the tier of the installed formwork in the elevator shaft.

External packages of formwork panels are mounted with the installation of DW1 ties, PVC-U pipes Ø 25 mm with BFD locks, RSS1 spacers fastened with NKD-S M20 anchors, TRG-120 scaffolding consoles are hung and a boardwalk is made along them according to the project.

The entire structure is brought into a strictly vertical position and is handed over for concrete work.

Concrete work is in progress.

Overlap

Installation and disassembly of the multiflex floor formwork is carried out in accordance with the technological map.

DISMANTLING OF THE FORMWORK.

Dismantling the formwork of columns, walls and an elevator shaft should be started when the concrete reaches a strength of 1.5 MPa, the overlap is 15 MPa.

The sequence of dismantling the formwork.

COLUMN

A block of two internal shields is dismantled

The next block of two shields is dismantled

STEN

The inner row of shields is dismantled

End and corner shields

Outdoor block of shields.

ELEVATOR SHAFT

The block of the internal formwork is dismantled

The outer formwork is dismantled.

Overlap

The intermediate racks are dismantled

The main stands are lowered by 4 cm

The cross beams are dismantled

Formwork panels are being dismantled

Formwork panels are being dismantled

The main beams are dismantled

The racks are dismantled.

The sequence of operations when dismantling the formwork.

COLUMN

Remove the panel board

Remove scaffolding consoles

Loosen the column bolts on the two-shield block

Sling a block of two panels using TRIO hooks, disconnect the leveling rods from the mount

With the help of a tower crane, lower it to the storage area to prepare for the next concreting.

Sling the next block of two panels, disconnect the leveling rods and lower it with a tower crane to the storage area.

WALLS

Remove the panel board

Remove scaffolding consoles

Rope the inner panel block of three panels with two TRIO hooks

Remove the BFD locks from the block of panels connecting to the next block of panels, disconnect the rods and locks, leveling the rods

Using a crane, release the block of three panels and lower it onto the storage area.

Repeat all operations with the following shield blocks

Sling end shield

Free it from strains and constipation and lower it to the storage area using a tower crane

Sling an outdoor block of three panels

Remove the leveling rods, BFD locks fastening to the next block of panels and using a crane lower to the storage area

Repeat these operations with the following blocks of external panels.

ELEVATOR SHAFT

Remove the tightening rods, constipation.

To sling indoor unit formwork with four sling hooks and with the help of a crane remove the entire block from the elevator shaft and put it on the storage area for subsequent preparation.

Sling the end block with the uncoupling element and use a crane to remove it from the shaft and lower it to the storage area

Remove the panel board and scaffold brackets from the next outer wall of the lift

Rope this block with two TRIO hooks

Remove the leveling rods and use a tower crane to remove the unit from the elevator shaft and lower it to the storage area

Repeat these operations with the next block of the outer wall of the lift.

Overlap

Dismantle the formwork according to the technological map.

Safety precautions.

At the seizure, where assembly work, it is not allowed to perform other work and find unauthorized persons.

Cleaning of the structural elements to be installed from dirt and ice should be carried out before lifting them.

Stay of people on structural elements during their lifting and movement is not allowed.

It is not allowed to find people under the elements to be mounted before installing them in the design position and securing them.

To make loosening of formwork blocks from assembly towers H = 2.5m (5.14 D of catalog 2617-961-89), external panels from block decks.

It is not allowed to carry out installation work at a height in open places with a wind speed of 15 m / s or more, with ice, thunderstorms, fog, excluding visibility within the work front. Work on moving formwork panels with high windage should be stopped at a wind speed of 10 m / s.

During the installation of the formwork, the installers must be on previously installed and securely fixed structures or scaffolds.

When installing panels with high windage, it is necessary to use guy wires to keep the panel from swinging.

Every day, before starting work, the foreman (foreman) must check the condition of the assembled panels and formwork blocks, working platforms, hanging platforms and stairs.

It is prohibited to carry out welding and gas-flame work of wooden formwork without appropriate safety measures.

Perform the work in accordance with the requirements of SNiP 3.03.01-87 "Supporting and enclosing structures", SNiP 12.03-2001 part 1, SNiP 12.03-2001 part 2 "Labor safety in construction", SNiP 21.01 - 97 "Fire safety of buildings and structures" , SNiP 2.02.02-85 * "Fire safety standards".

Technological map for concrete work of a monolithic house in the formwork "PERI"

Concreting of columns, walls and ceilings should be carried out with grapples. Each floor is divided in the plan into 2 captures. The working seam is specified in the project. During the installation of the reinforcement at the border of the grips in the overlap, install a woven mesh GOST 3826-82, tying it to the reinforcement with a knitting wire. The resumption of concreting in the places of the construction of working seams is allowed when the concrete reaches a strength of 1.5 MPa. To clean the working joints from the cement film with an air jet from the compressor. It is allowed to arrange working seams - for columns and walls at the level of the bottom of the floor slab, for overlapping in the middle of the span 3-4 or 4-5 - parallel to the digital axes. In the initial period of concrete hardening, it is necessary to protect against atmospheric precipitation or moisture loss.

Before the start of concreting, the following work must be performed on each grip:

Installation and alignment of formwork

Fitting installation

The certificate of examination has been drawn up hidden works for the installation of fittings, embedded parts, corrugated power supply pipes, formwork.

When concreting the columns, use concrete of class B 20, frost resistance grade F50; internal walls (diaphragms) - concrete of class B 20, frost resistance grade F50; elevator shafts - concrete of class B20, frost resistance grade F50; floors - concrete of class B20, frost resistance grade F50.

The movement of people on the concreted structures and the installation of the formwork of the overlying structures is allowed when the concrete reaches a strength of at least 15 MPa.

The concrete is delivered to the construction site in auto mixers. At the construction site, organize a place for receiving concrete from auto mixers in the form of two bunkers. For uniform distribution of concrete in the formwork of walls and columns, unload the concrete into funnels installed in the formwork.

Reinforcement of walls and columns to be carried out directly on the gripper manually from separate rods and frames, having previously fed the blanks with a crane to the overlap. The fixation of the frames in relation to the edges of the wall in order to form a protective layer should be carried out using clamps according to brands, depending on the diameter of the reinforcement on which it is put on and the thickness of the protective layer of concrete. Concrete placement within the work area should be done in horizontal layers 500 mm thick. When compaction concrete mix the immersion depth of the vibrator should ensure its immersion into the previously laid layer by 5-10 cm. The step of repositioning the vibrators is not more than 1.5 of its radius of action. Vibrate until the end of the appearance of air bubbles on the concrete surface, vibrate especially carefully in the corners of the formwork.

Floor slab reinforcement to be made of frames and meshes made at the factory (reinforcement yard of the construction site). The nets and frames are transported by a tower crane to workplace and mounted in the following sequence:

A row of bottom grids are installed

Support frames are installed

The upper grids are mounted.

The assembly of space frames into volumetric ones is carried out using a knitting wire. Fixation of the lower nets in relation to the overlap plane in order to form a protective layer using plastic clamps (TU 6-05-160-77). Simultaneously with the installation of the reinforcement, lay horizontal PVC pipes to skip electrical communications. Pull the wire into the tubes before laying. Attach the tubes to the armature with a knitting wire. At the same time, all embedded parts are installed in the formwork according to the project. Concrete placement within the designated work area should be carried out to the depth of the floor thickness without breaks, with a sequential direction of placement in one direction. The height of free concrete dumping from the bunker is not more than 1m. vibrate until air bubbles appear on the concrete surface, until cement laitance appears.

Safety precautions.

    The place for receiving concrete should be made with a fence on three sides, except for the side of the entrance of cars, on this side signs "Caution, possible fall" are installed.

    Climb the scaffolding using inventory stairs.

    When compacting the concrete mixture, it is not allowed to rest the vibrators on reinforcement and embedded products, rods and other formwork fastening elements.

    Every day, before starting to place concrete in the formwork, it is necessary to check the condition of the container, formwork and paving equipment. Found faults must be rectified immediately.

    When compacting concrete with electric vibrators, it is not allowed to move the vibrator by the current-carrying hoses, and during breaks in work and when moving from one place to another, the electric vibrators must be turned off.

    Placement of equipment and materials on the formwork that are not provided for by the project for the production of work, as well as the presence of unauthorized persons is not allowed.

    Before starting work on the installation of reinforcement, a fence should be installed on each grip on the perimeter ceiling.

8. Perform the work in accordance with the requirement of SNiP 3.03.01-87 "Bearing and enclosing structures", SNiP 12.03-2001 part 1, SNiP 12.03-2001 part 2 "Labor safety in construction", SNiP 21.01-97 "Fire safety of buildings and structures ", SNiP 2.02.02-85 *" Fire safety standards ".

One of the first stages in the construction of structures for various purposes is the installation of formwork. This process is often overlooked. But already at the stage of preparation for pouring it becomes clear that not everything is as simple as it was thought at first. The installation instructions for the formwork will help to assemble the frame.

Formwork types

There are three types of construction:

  • Removable, which is dismantled after the solution has completely dried. Such formwork is assembled from separate parts. The result is a collapsible structure that can be dismantled and reused. Among the advantages of this type of formwork are the ease of installation, the possibility of reuse, which significantly reduces the financial costs of construction.
  • Fixed, respectively, the one that is not dismantled. Installation of this type of formwork is carried out mainly from expanded polystyrene or polystyrene foam. It remains part of the structure under construction. And at the same time it acts as a heater.
  • "Floating" formwork is typical for the construction of a monolithic foundation, which is immersed in the ground. It is a board assembled from boards, which is slightly higher in height than the planned concrete structure. The shield is lowered into the pit and attached to its walls. Cardboard or roofing material is rolled over it.

There are also several types, depending on the purpose:

  • Wall formwork. Installation is carried out for the construction of vertical structures and walls.
  • Horizontal, which is used for the installation of foundations and floors.
  • Curved, which allows you to fill in details of unusual shapes.

Installation and dismantling of each type of formwork has its own characteristics. You need to know them for quality work.

The advantages of permanent formwork

Installation of permanent formwork involves the purchase of a ready-made set for the performance of work. It remains only to assemble the structure and install it. This implies a number of advantages that this type of formwork has:

  • short terms of work execution;
  • ease of installation;
  • low weight of the structure;
  • resistance to the appearance of fungus and mold;
  • fire safety;
  • low cost.

Also, permanent formwork is at the same time a layer of insulation and is a foam block that is easily connected to each other. Moreover, the inner wall is thinner than the outer one. This achieves a high level of thermal insulation.

Erection of permanent formwork

The finished shields are attached to the corner bars with self-tapping screws or nails. The fastening must be secure. As the concrete expands, the pressure on the shield will increase, which can lead to cracking of the boards. The main thing is that the bar itself remains with outside... In parallel to the assembled structure, another row is assembled at the distance of the future wall. As a result, you should get a frame around the entire perimeter.

A layer of crushed stone or sand is poured into the finished formwork box. This will protect the mortar from moisture loss, which will go into the ground. The formwork installation technology provides for protection against the flow of mortar through the existing holes. For this, the boards are covered with a film or roofing felt, which are fastened with screws or staples using a stapler.

All work must be carried out taking into account the level. It is very important. At each stage, the evenness of the structure in height, length and vertical is checked (especially important). Two rows of shields should run strictly parallel to each other.

Basic formwork elements

Removable formwork, which is assembled independently, consists of the following elements:

  • Deck, which is a flat panel that is the entire form of enclosure. The structure must be strong enough to withstand the pressure of the mortar. Therefore, it is made from plywood or edged boards 4-5 cm thick.
  • Scaffolding, which are the support of the structure. They hold the walls in place, preventing the mortar from squeezing out the deck. Scaffolding is made from pine blocks or boards (2.5-5 cm).
  • Fasteners are all the parts with which all structural elements are twisted: wire, clamps, ties, hardware, and so on.

The deck is most often assembled from planks 15 cm wide, which are connected in several rows using nails (driven in from the inside, bent from the outside) or self-tapping screws (they are screwed with inside). The distance between the boards should not exceed 3 mm. Shields are fastened together with additional strips.

A simpler option for making a deck is to use moisture-resistant plywood with a thickness of 1.8-2.1 cm.

Formwork installation

The frame will be installed evenly and level if the site has been properly prepared in advance. It is marked out using cords stretched between the pegs. The sand cushion is filled up and compacted. If necessary, a foundation pit is prepared.

The installation of the formwork takes place in the following sequence:

  • The perimeter should be marked with vertical guides ( wooden blocks, metal corners or pipes).
  • It is required to place ready-made panels along the guides, maintaining the required distance between them (it is equal to the required thickness of the foundation).
  • Fix the deck firmly. Support it from the outside with inclined beams (1 brace for each meter of deck).
  • Connect the shields to each other with 5x5 cm bars.
  • Cover the inner side of the formwork with foil (roofing felt).

Foundations up to 20 cm high do not require serious construction. For them, the bars driven into the ground are enough.

Installation of wall formwork

The process of erecting wall formwork is more complicated. At the same time, small-panel and large-panel formwork are distinguished.

The first option is suitable for the construction of small buildings ( country houses, utility buildings) and partitions between rooms. In this case, small-sized plywood boards are used.

Installation of large-panel formwork is typical for the construction of buildings with high heights. For work, use sheets of metal or large sheets of plywood.

For the installation of the walls, a foundation is prepared into which the reinforcement is stuck. A two-row formwork frame is assembled around it. When using ordinary plywood, the joints are coated with glue or sealant. There is currently a special formwork plywood on the market. Its individual sheets are connected according to the “thorn-groove” principle, which does not require additional sealing.

Floor types

Installation of slab formwork depends on the type of slab itself. The following types of structures are distinguished:

  • On bulky bowls. It is used for structures with high heights. In this case, vertical posts, jacks, inserts, crossbars and other elements are used to connect individual parts.
  • On blade scaffolds that are used for multi-storey buildings... Scaffolds are installed instead of plywood boards.
  • On cup-type forests. This view provides for the installation of the frame. The racks are connected to each other by the cup method.
  • On telescopic bowls. Suitable in cases where the floor height is less than 4.6 m. It is based on tripods that support the entire structure. Shields of moisture-resistant plywood are laid on top.

Slab formwork

Currently, monolithic flooring is most often used. Using his example, we will analyze the formwork installation process.

For the formwork, vertical posts are used, interconnected by crossbars. They are attached at right angles to the bars running in the transverse direction. A plywood board is laid on these transverse beams, which is the bottom of the formwork.

To carry out these works, the following materials are used:

  • rack - a bar with a cross section of 12-15 cm;
  • transom and cross beam - edged board 16-18 cm wide and 5 cm thick;
  • braces - board 3 cm thick;
  • flooring - moisture resistant 1.8 cm thick.

Before starting work, it is necessary to carry out accurate calculations. It is important to define required amount racks, the step of their placement and other indicators.

Slab Formwork Installation Instructions

The work instruction includes the following steps:

  • Longitudinal beams are attached to the upper part of the racks, the other end of which is fixed to the wall.
  • The second row is assembled in the same way. For this, a board 5 cm thick is laid under the supports.
  • The transverse beams are laid with a step of 60 cm.
  • Support posts are installed (strictly vertically).
  • The racks are interconnected with braces.
  • Plywood sheets are laid on the transverse bars, leaving no gaps.
  • The ends of the slab are protected by masonry from blocks or bricks.
  • The frame is assembled from reinforcement. At the same time, if necessary, they leave space for communications.

When all the work is completed, concrete can be poured. Remove the formwork after 3 weeks.

Conclusion

The installation of each type of formwork involves the use of certain materials. If boards are used, they must be new. Rotten old boards can fail and break. Plywood should be moisture resistant or laminated.

All work is required to be performed in accordance with the calculations made. This is especially important for the installation of floor and wall formwork.

Individual and industrial construction of multi-storey monolithic buildings, bridges and overpasses is carried out using formwork ceilings. They are easy to install and allow you to erect buildings of various shapes and sizes in various climatic zones with an ambient temperature of +45 to -40 degrees C.

Formwork on volumetric racks

Types of slab formwork

The use of different types formwork:

  • recommended for floors up to 5 meters high. They are the most economical of all formwork types and can be erected within a short period of time. The tripod base is reasonably stable and supports the main strut securely. Moisture-resistant plywood panels are placed on beams made of wood or metal profiles.
  • Volumetric props of floor formwork are erected at a height of up to 20 meters. Ease of installation is ensured by vertical posts connected with crossbars, flange and jack systems. According to the installation method, they are subdivided:
  1. on wedge-shaped scaffolds - with a frame of horizontal and vertical posts that can be installed under different angles, depending on the complexity of the work performed at different construction sites. The scaffolding and working ladders provide the necessary level of safety for the working personnel.
  2. with cup scaffolding - allowing to install up to 4 structural elements on one level.

The device of volumetric racks

The main starting post is mounted on the jack, onto which additional posts of different lengths are attached to the flanges. In the same flanges, horizontal girders are installed, fastening the formwork sections. Additional posts and crossbars of different lengths allow the construction of sectional groups of various sizes. The top of the structure is crowned with a jack with a fork, on which wooden or metal deck beams are attached.

The starting and additional posts are made of metal, which provides the necessary rigidity of the structure. It can be reinforced with additional special flanges installed one meter apart. Ease of installation is provided by one tapered end of the rack. The uniformity of the load distribution is guaranteed by the wedge clamps, which also increase the reliability and strength of the entire structure.

Specifications:

  • Maximum height limit, m - 20.
  • The minimum height limit, m - 1.5.
  • Rack pitch, m - 1.0; 1.25; 1.5; 1.75; 2.0; 2.5; 3.0.
  • The maximum limit of the distributed load on the girder, kg - 1200.
  • Allowable turnover - 100 cycles.
  • The maximum turnover is 200 cycles.
  • Section height, m ​​- 0.5.

The calculation of the formwork for construction depends on the total area of ​​the building being erected and the axle load. For ease of installation, the distance between the racks is from 1 to 3 meters in half-meter increments. Plywood sheet is selected taking into account the trimmings to fit on the installed sites.

The advantages of volumetric slab formwork props:

  • Operational safety due to rigid and reliable fastening.
  • The ability to move individual units without disassembling them using lifting devices.
  • Ease of assembly and disassembly using universal fasteners for the entire system.
  • Most effective when working at high altitudes.
  • It can be used for finishing works.
  • Long-term - up to a maximum of 200 cycles.
  • The ability to develop individual design solutions in construction.

Manufacturers of volumetric slab formwork offer not only standard sizes of all components, but they also manufacture structures according to the orders of construction organizations. It is possible to purchase a ready-made set or rent it, which will significantly reduce the monetary costs of construction.

Regulatory documentation for slab formwork

Each manufacturer prepares its own internal standards for the production of structural elements. All components of the formwork must comply with the requirements for products of hazard class 2 in accordance with GOST R 52085 - 2003, which must be confirmed by a certificate from the regional agency Rosstandart. The technological process of production is strictly regulated by the company's specialists at every stage.

When installing the structure and working at height, the safety requirements must be observed. All actions must be carried out in special protective clothing and using personal protective equipment. Employees should be familiar with the basic technical documentation and have permits to work.

How to make volumetric formwork yourself


It is much more economical to make the formwork with your own hands when building a private house. But at the same time, the following nuances should be taken into account:

  • Particular attention should be paid to the installation of support legs that carry the main load. Metal supports provide reliability, but working with them is a little more difficult than with wooden ones.
  • Ensure the rigidity of the installation of the base. For this, the installation is carried out on a carefully prepared site - irregularities are tamped and wooden gaskets are laid along the axes.
  • The longitudinal beams are attached to the uprights on metal corners using bolted connections.
  • The cross beams do not need to be secured, but simply stacked on the longitudinal beams. This helps to facilitate the dismantling process after all work has been completed.
  • With the help of braces, the support racks and longitudinal beams are fixed.
  • Plywood should be laid tightly to each other, carefully watching the joints, which should be strictly on the floor beam.
  • The most optimal distance between the posts is 1.5 meters.
  • The alignment of the entire structure is carried out using a level or a level and a plumb line.
  • Installation of each subsequent tier should be done after carefully fixing and checking the previous one.

For the manufacture of formwork, you can use the available lumber, but they must not be rotten and thoroughly dried from coniferous wood. The bars of the racks must have a cross section of at least 12 * 12 cm, and the beam 16 * 16 cm.

Dismantling the formwork

Dismantling work depends on the drying time of the concrete or the completion of the necessary finishing activities. In hot summer weather, the formwork can be removed after 3 - 4 days. All work is carried out in the reverse order that was carried out during assembly. The formwork can then be reused. For this, all elements should be marked, sorted and cleaned from all contaminants.

Installation and dismantling of volumetric slab formwork is a rather troublesome and complicated matter. The utmost attention and concentration is required during assembly, on which the life and health of workers can depend. But with some knowledge of technology and required materials, it is possible on their own carry out all the required work on schedule.

The installation of the formwork is carried out using a KB 403 tower crane with a boom length of 30 m, installed according to the construction plan. The installation of the formwork should be carried out according to the grips. Each floor is divided into two sections in the plan.

Columns, walls and ceilings are to be concreted in the "Peri" formwork. The formwork kit consists of:

  • - WALL - made of metal panels lined with water-resistant plywood 21 mm thick, withstanding the pressure of freshly laid concrete of 60 kN / m 2; straightening locks BFD, providing in one operation the connectivity, evenness and density of the formwork panels; strands DV - 15 with a nut - gasket with a permissible load on the strand of 90 kN; leveling tie rod PCC with a support, ensuring the stability of the formwork structures and designed for a load of 30 kN; consoles of suspended scaffolding TRZh 120, ensuring safety when the load on the platform is 150 kg / m 2.
  • - COLUMN - metal panels TRS, lined with waterproof plywood 21 mm thick, withstanding the permissible pressure of freshly laid concrete of 100 kN / m 2, column tension bolts with a permissible bolt load of 90 kN.
  • - COVERINGS - made of lattice girders GT 24 of various lengths with a bearing capacity - transverse force in struts - 14 kN, bending moment - 7 kNm, supports PER 30 with a bearing capacity of 30 kN; panels made of waterproof plywood 21 mm thick.

The formwork is delivered to the construction site in special containers by road and stored under a canopy.

See below for the formwork installation scheme, it shows the arrangement of work tables and installation and docking of PERI carts.

Before starting the installation of the formwork on the grip, it is necessary to perform:

  • - to concrete a reinforced concrete slab with reinforcement outlets for columns, walls, an elevator shaft;
  • - apply the risks of the alignment axes to the reinforced concrete slabs;
  • - to apply the concrete-separating liquid "Pera-Wedge" to the formwork panels using a spray gun;

installation of design fittings;

delivery of tools, devices and equipment to the workplace.

Formwork installation scheme.

The sequence of formwork installation at the grip:

WALLS and COLUMNS:

  • - install the block of outer formwork panels on the spacers;
  • - install fittings;
  • - to install the block of internal panels on straps and locks with hanging of the scaffolding and flooring consoles.

The transfer of the main axes of the building to the slab is carried out from the benchmarks. All other building axes are set out from the main axes of the measurement paths. Control over the erection of a monolithic house vertically is carried out floor by floor by theodolites using the oblique design method.

When performing geodetic works, it is necessary to be guided by SNiP 3.01.03 - 84 "Geodetic works in construction".

To reduce the adhesion of the deck to the concrete surface, thoroughly clean it and spray it with Peri-Klin concrete release fluid. Clean immediately after removing the formwork by spraying with water, then with a rubber-tipped scraper and a hair brush and spraying with concrete release agent. Apply the concrete release fluid with a hand-held spray gun. Apply at the storage site (in winter - in a warm room). Provide measures to prevent the lubricating film from being washed off by rain.

Slinging of the formwork is carried out using a special TRIO hook included in the formwork kit and a transport sling with four ropes. To lift the panels, use two TRIO crane hooks (load-bearing capacity of one hook - 1.5 t).

See below for the slinging scheme of formwork elements.

The lifting of small and piece elements should be carried out in containers.

Slinging scheme of formwork elements.

The sequence of operations during the installation of wall formwork:

  • - the position of the diaphragm is marked on the spot, using perforators, holes W = 25 mm 90 mm deep are drilled in reinforced concrete slabs to install NKD-S M 20 anchors.
  • - on the stand, in a horizontal position, a package of shields (3 pcs.) is assembled, connected by BFP locks with RSS1 struts attached to them.
  • - by means of crane hooks of the "Peri" system (2 pcs. per transport unit), the package of shields is lifted to a vertical position and transported by a crane to the installation site.
  • - the package of shields is installed according to the risks in the design position on the outer section of the diaphragm and is fastened with RSS1 spacers with NKD-S M20 anchors to the reinforced concrete slab. Separate panels or panels are docked to the installed formwork, depending on the length of the diaphragm, and fastened together with BFD locks in the amount specified in the project.
  • - the entire structure is brought to a vertical position with the help of RSS1 struts, and then reinforcement work is started.
  • - after the completion of the reinforcement work, the inner row of formwork panels is mounted, connected to the previously installed panels using DW-15 straps and washer nuts, with the installation of PVCVH pipes W = 25 mm in length to the thickness of the diaphragm.
  • - then the end shields Shch-1 are installed, connected to the formwork shields with BFD locks and TAR-85 leveling locks, scaffolding brackets TRG - 120 and wooden flooring 35 - 40 mm thick are hung.

The entire structure is finally brought to a strictly vertical position and is handed over for concrete work.

COLUMNS:

  • - reinforcement work is being carried out.
  • - on a horizontal stand, a formwork block is assembled from two panels connected by column bolts.
  • - using a crane equipped with two-hook TRIO slings, the unit is brought to a vertical position and installed on a horizontal platform and temporarily fixed to the base with a spacer RSS1.
  • - the third shield is mounted.
  • - a block of three panels is transported to the installation site using a tower crane with two TRIO hooks and mounted to the design position, with the RSS1 spacer fastening to the floor slab.
  • - the fourth shield is mounted and secured by the RSS1 spacer.
  • - scaffolding consoles are hung, and scaffolding panel boarding is performed.
  • - the formwork is brought into a strictly vertical position using the RSS1 spacers. The formwork is ready for concreting the elevator shaft.

The internal elevator shafts are marked on the foundation slab.

On the stand, in a horizontal position, four packages of panels are assembled to the length of the inner wall of the elevator shaft with fastening to each other with BFD locks according to the project.

With the help of crane hooks of the TRIO system (2 pcs. Per transport unit), the package is lifted to a vertical position and transported to the installation site by a tower crane. The package is installed in the design position with temporary fastening of the RSST brace to the reinforced concrete slab. Then the rest of the panels are installed and connected with BFD locks according to the project.

Reinforcement works are in progress.

After the completion of the reinforcement work, the external formwork panels of the elevator shaft are installed, connected to the previously installed formwork with DW 15 ties with washer nuts and PVC-U pipes Ø 25 mm long by the thickness of the elevator wall, leveling locks TAR - 85 and between themselves with BFD locks according to the project.

The braces RSS1 are installed, the scaffolds TRG-120 are suspended and the boardwalk is made according to the project.

With the help of RSS1 struts, the structure is brought into a vertical position and handed over for concrete work.

Concrete work is in progress.

Sequence of installation of the elevator shaft formwork from elevation +0.000

Support elements (stand-stop) are installed in the upper holes, freed from the straps, to support the next tier of the formwork according to the project.

The device of the flooring in the elevator shaft and in the staircase for the production of installation and reinforcement works is being carried out.

The internal formwork of the elevator shaft (assembled) is mounted using a tower crane on the installed supporting elements (stop-posts) in the elevator shaft.

Reinforcement work is being carried out on the tier of the installed formwork in the elevator shaft.

External formwork panels are mounted with the installation of DW1 ties, PVC-U pipes Ø 25 mm with BFD locks, RSS1 spacers with NKD-S M20 anchors, TRG-120 scaffolding brackets are hung and a boardwalk is made along them according to the project.

The entire structure is brought into a strictly vertical position and is handed over for concrete work.

Concrete work is in progress.

Overlap

Installation and disassembly of the multiflex floor formwork is carried out in accordance with the technological map.

DISMANTLING OF THE FORMWORK.

Dismantling the formwork of columns, walls and an elevator shaft should be started when the concrete reaches a strength of 1.5 MPa, the overlap is 15 MPa.

The sequence of dismantling the formwork.

  • - dismantled a block of two internal shields
  • - the next block of two shields is dismantled
  • - the inner row of shields is dismantled
  • - end and corner shields
  • - outdoor block of shields.

ELEVATOR SHAFT

  • - dismantled block of internal formwork
  • - the outer formwork is dismantled.

Overlap

  • - intermediate racks are dismantled
  • - the main racks are lowered by 4 cm
  • - the cross beams are dismantled
  • - formwork panels are dismantled
  • - formwork panels are dismantled
  • - the main beams are dismantled
  • - racks are dismantled.

The sequence of operations when dismantling the formwork.

  • - remove the panel board
  • - remove the scaffolding consoles
  • - release the column bolts on the block of two shields
  • - tie up a block of two panels using TRIO hooks, disconnect the leveling rods from the mount
  • - using a tower crane to lower it to the storage area to prepare for the next concreting.
  • - to sling the next block of two panels, disconnect the leveling rods and lower it with a tower crane to the storage area.
  • - remove the panel board
  • - remove the scaffolding consoles
  • - tie the inner panel block of three panels with two TRIO hooks
  • - remove the BFD locks from the block of shields connecting to the next block of shields, disconnect the rods and locks, leveling the rods
  • - using a crane, release the block of three panels and lower it onto the storage area.
  • - repeat all operations with the following shield blocks
  • - to sling the end shield
  • - release it from strains and constipation and, using a tower crane, lower it to the storage area
  • - to sling an outdoor block of three panels
  • - remove the leveling rods, BFD locks fastening to the next block of shields and using a crane to lower them onto the storage area
  • - repeat these operations with the following blocks of external panels.

ELEVATOR SHAFT

  • - remove tightening rods, constipation.
  • - hook the inner formwork block with four sling hooks and use a crane to take the entire block out of the elevator shaft and put it on the storage area for subsequent preparation.
  • - sling the end block with the unloading element and with the help of a crane take it out of the shaft and lower it onto the storage area
  • - remove the panel board and scaffold consoles from the next outer wall of the lift
  • - attach this block with two TRIO hooks
  • - remove the leveling rods and, using a tower crane, remove the block from the elevator shaft and lower it onto the storage area
  • - repeat these operations with the next block of the outer wall of the lift.

Overlap

Dismantle the formwork according to the technological map.

Safety precautions.

At the seizure, where installation work is being carried out, it is not allowed to perform other work and the presence of unauthorized persons.

Cleaning of the structural elements to be installed from dirt and ice should be carried out before lifting them.

Stay of people on structural elements during their lifting and movement is not allowed.

It is not allowed to find people under the elements to be mounted before installing them in the design position and securing them.

To make loosening of formwork blocks from assembly towers H = 2.5m (5.14 D of catalog 2617-961-89), external panels from block decks.

It is not allowed to carry out installation work at a height in open places with a wind speed of 15 m / s or more, with ice, thunderstorms, fog, excluding visibility within the work front. Work on moving formwork panels with high windage should be stopped at a wind speed of 10 m / s.

During the installation of the formwork, the installers must be on previously installed and securely fixed structures or scaffolds.

When installing panels with high windage, it is necessary to use guy wires to keep the panel from swinging.

Every day, before starting work, the foreman (foreman) must check the condition of the assembled panels and formwork blocks, working platforms, hanging platforms and stairs.

It is prohibited to carry out welding and gas-flame work of wooden formwork without appropriate safety measures.

Perform the work in accordance with the requirements of SNiP 3.03.01-87 "Supporting and enclosing structures", SNiP 12.03-2001 part 1, SNiP 12.03-2001 part 2 "Labor safety in construction", SNiP 21.01 - 97 "Fire safety of buildings and structures" , SNiP 2.02.02-85 * "Fire safety standards".

Routing for concrete work of a monolithic house in the formwork "PERI"

Concreting of columns, walls and ceilings should be carried out with grapples. Each floor is divided in the plan into 2 captures. The working seam is specified in the project. During the installation of the reinforcement at the border of the grips in the overlap, install a woven mesh GOST 3826-82, tying it to the reinforcement with a knitting wire. The resumption of concreting in the places of the construction of working seams is allowed when the concrete reaches a strength of 1.5 MPa. To clean the working joints from the cement film with an air jet from the compressor. It is allowed to arrange working seams - for columns and walls at the level of the bottom of the floor slab, for overlapping in the middle of the span 3-4 or 4-5 - parallel to the digital axes. In the initial period of concrete hardening, it is necessary to protect against atmospheric precipitation or moisture loss.

Before the start of concreting, the following work must be performed on each grip:

  • - installation and alignment of formwork
  • - installation of fittings
  • - an act of inspection of hidden works for the installation of fittings, embedded parts, corrugated power supply pipes, and formwork was drawn up.

When concreting the columns, use concrete of class B 20, frost resistance grade F50; interior walls(diaphragms) - concrete of class B 20, frost resistance grade F50; elevator shafts - concrete of class B20, frost resistance grade F50; floors - concrete of class B20, frost resistance grade F50.

The movement of people on the concreted structures and the installation of the formwork of the overlying structures is allowed when the concrete reaches a strength of at least 15 MPa.

The concrete is delivered to the construction site in auto mixers. At the construction site, organize a place for receiving concrete from auto mixers in the form of two bunkers. For uniform distribution of concrete in the formwork of walls and columns, unload the concrete into funnels installed in the formwork.

Reinforcement of walls and columns should be carried out directly on the gripper manually from individual rods and frames, after having supplied the blanks with a crane to the ceiling. The fixation of the frames in relation to the edges of the wall in order to form a protective layer is carried out with the help of clamps according to brands, depending on the Ш of the reinforcement on which it is put on and the thickness of the protective layer of concrete. Concrete placement within the work area should be done in horizontal layers 500 mm thick. When compacting the concrete mixture, the immersion depth of the vibrator must ensure its immersion into the previously laid layer by 5-10 cm. The step of repositioning the vibrators is not more than 1.5 of its radius of action. Vibrate until the end of the appearance of air bubbles on the concrete surface, vibrate especially carefully in the corners of the formwork.

Reinforcement of the floor slab is made of frames and meshes made at the factory (reinforcement yard of the construction site). The nets and frames are transported by a tower crane to the workplace and mounted in the following sequence:

  • - a number of lower grids are installed
  • - support frames are installed
  • - the upper grids are mounted.

The assembly of space frames into volumetric ones is carried out using a knitting wire. Fixation of the lower nets in relation to the overlap plane in order to form a protective layer using plastic clamps (TU 6-05-160-77). Simultaneously with the installation of fittings, lay horizontal PVC pipes for the passage of electrical communications. Pull the wire into the tubes before laying. Attach the tubes to the armature with a knitting wire. At the same time, all embedded parts are installed in the formwork according to the project. Concrete placement within the designated work area should be carried out to the depth of the floor thickness without breaks, with a sequential direction of placement in one direction. The height of free concrete dumping from the bunker is not more than 1m. vibrate until air bubbles appear on the concrete surface, until cement laitance appears.

Safety precautions.

  • 1. The place for receiving concrete should be made with a fence on three sides, except for the side of the entrance of cars; on this side, signs "Caution, possible fall" are installed.
  • 2. Climb the scaffolding using inventory stairs.
  • 3. When compacting the concrete mixture, it is not allowed to rest the vibrators on the reinforcement and embedded products, rods and other elements of the formwork fastening.
  • 4. Every day, before starting to place concrete in the formwork, it is necessary to check the condition of the container, formwork and paving equipment. Found faults must be rectified immediately.
  • 5. When compacting concrete with electric vibrators, it is not allowed to move the vibrator by the current-carrying hoses, and during breaks in work and when moving from one place to another, the electric vibrators must be turned off.
  • 6. Placement of equipment and materials on the formwork not provided for by the project for the production of works, as well as the presence of unauthorized persons is not allowed.
  • 7. Before starting work on the installation of the reinforcement, on each grip on the perimeter ceiling, install a fence.
  • 8. Perform the work in accordance with the requirement of SNiP 3.03.01-87 "Bearing and enclosing structures", SNiP 12.03-2001 part 1, SNiP 12.03-2001 part 2 "Labor safety in construction", SNiP 21.01-97 "Fire safety of buildings and structures ", SNiP 2.02.02-85 *" Fire safety standards ".

CENTRAL RESEARCH AND DESIGN AND EXPERIMENTAL INSTITUTE OF ORGANIZATION, MECHANIZATION AND TECHNICAL ASSISTANCE TO CONSTRUCTION

AOZT TsNIIOMTP

ROUTING
ON THE DEVICE OF COLUMN MONOLITHIC FOUNDATIONS USING A SMALL-SHIELD FORMWORK

Moscow

In the technological map, the device of columnar monolithic foundations for reinforced concrete columns using metal formwork is considered.

The organization and technology of construction processes are given, the basic safety rules are indicated. Constructive schemes for the organization and technology of work are presented.

The technological map was developed by AOZT TsNIIOMTP (B.V. Zhadanovsky head department, cand. tech. sciences, O.V. Baranov, L.V. Zhabina with the participation of the head. the computer and information technology sector Yagudaeva L.M.).

1 AREA OF USE

1.1. The technological map was developed for the installation of columnar monolithic foundations for the frame of civil and industrial buildings using small-panel formwork.

1.2. The technological map provides for the construction of monolithic foundations using small-panel formwork developed by AOZT TsNIIOMTP (project 794V-2.00.000).

1.3. The foundation of series 1-412 with a volume of 14.7 m 3 was taken as a reference in the development of the map.

1.4. The flow chart considers the options for supplying concrete mixture in the structure:

truck crane in bunkers;

concrete pump SB-170-1.

1.5. Concrete mix transportation is provided by the SB-159B-2 concrete mixer truck.

1.6. The work is carried out in two shifts in the summer.

2. ORGANIZATION AND TECHNOLOGY OF WORK PERFORMANCE

2.1. Before starting the construction of the foundations, the following work must be performed:

drainage of surface water from the site was organized;

access roads and highways are arranged;

the paths of movement of mechanisms, places of storage, enlargement of reinforcing nets and formwork are indicated, assembly equipment and devices are prepared;

Reinforcement meshes, frames and formwork kits were delivered in the required quantity;

the necessary preparation for the foundations has been completed;

geodetic breakdown of axes and marking of the position of foundations in accordance with the project;

on the surface of the concrete preparation, there are painted risks that fix the position of the working plane of the formwork panels.

2.2. The prepared foundation for the foundations must be accepted by an act by the commission with the participation of the customer, the contractor and the representative of the design organization. The act must reflect the correspondence of the location, elevations of the bottom of the pit, the actual bedding and natural properties soils according to the project, as well as the possibility of laying foundations at the design level, the absence of violations of the natural properties of base soils or the quality of their compaction in accordance with design solutions.

2.3. Acts for hidden works should be drawn up for the preparation device for foundations.

2.4. Before installing the formwork and reinforcement of reinforced concrete foundations, the work manufacturer (foreman, foreman) must check the correctness of the concrete preparation device and marking the position of the axes and marks of the base of the foundations.

Formwork works

2.5. The formwork should be delivered to the construction site as a complete set, suitable for installation and operation, without any modifications or corrections.

2.6. The elements of the formwork that arrived at the construction site are placed in the area of ​​operation of the assembly crane. All elements of the formwork must be stored in a position corresponding to the transport, sorted by brands and standard sizes. It is necessary to store the elements of the formwork under a canopy in conditions that exclude their damage. Shields are stacked in stacks no more than 1 - 1.2 m high on wooden pads; fights of 5 - 10 tiers with a total height of no more than 1 m with the installation of wooden spacers between them; the rest of the elements, depending on the size and weight, are placed in boxes.

2.7. Small-panel formwork consists of the following components:

linear panels are made of a bent profile (channel), the deck in the panels is made of laminated plywood 12 mm thick;

load-bearing elements - clamps are designed to absorb the loads acting on the formwork, as well as to combine individual panels into panels or blocks. They are made of a bent profile (channel);

corner shields - are used to combine flat shields into closed contours;

assembly corner - serves to connect boards and panels into closed formwork contours;

tension hook - used to attach contractions to shields;

bracket - serves as the basis for the working platform.

2.8. Mounting and dismantling of the formwork is carried out using a vehicle crane KS-35715 or KS-45719, KS-4572A.

2.9. Before the start of the installation of the formwork, the panels are pre-assembled in the panels in the following sequence:

at the storage site, a box of contractions is assembled;

shields are hung on the fights;

on the edge of the panels of the panel, paint marks are applied, indicating the position of the axes.

2.10. The foundation formwork device is carried out in the following order:

the enlarged formwork panels of the lower step of the shoe are installed and fixed;

the assembled box is installed strictly along the axes and the formwork of the lower step is fixed with metal pins to the base;

apply risks to the edges of the enlarged panels of the box, fixing the position of the box of the second stage of the foundation;

stepping back from the marks at a distance equal to the thickness of the shields, a pre-assembled box of the second stage is installed;

the second stage box is finally installed;

the third stage box is installed in the same sequence;

risks are applied to the edges of the enlarged panels of the upper box, which fix the position of the box of the sub-column;

install the column column box;

install and secure the liner formwork.

The assembled formwork is accepted according to the act by the foreman or foreman.

2.11. The condition of the formwork must be monitored continuously during the concreting process. In the event of unforeseen deformations of individual formwork elements or inadmissible opening of gaps, additional fasteners should be installed and the deformed places should be corrected.

2.12. Dismantling of the formwork is allowed only after the concrete reaches the strength required in accordance with SNiP 3.03.01-87 and with the permission of the manufacturer of the work.

2.13. In the process of tearing off the formwork, the surface of the concrete structure should not be damaged. Dismantling of the formwork is carried out in the reverse order of installation.

2.14. After removing the formwork, you must:

make a visual inspection of the formwork;

clean all formwork elements from adhered concrete;

grease the decks, check and grease the screw connections.

2.15. Formwork production schemes are given in Fig. 15.

Reinforcement work

2.16. Reinforcing nets of sub-columns are delivered to the construction site and unloaded at the pre-assembly site, shoe nets - at the storage site.

2.17. The assembly of the reinforcement cages for the sub-column is carried out at the assembly stand with the help of a conductor, by tacking the reinforcing meshes between themselves by electric arc welding or viscous.

2.18. Reinforcing frames and nets of shoes weighing over 50 kg are installed with an automobile crane in the following order:

Reinforcement mesh of the shoe is laid on the clamps, which provide a protective layer according to the project.

2.19. Reinforcement work is performed in the following order:

install reinforcing mesh of the shoe on the clamps, providing a protective layer of concrete according to the project;

after the device of the shoe formwork, reinforcing pillars are installed with fastening it to the lower mesh with a knitting wire.

2.20. Reinforcement works must be carried out in accordance with SNiP 3.03.01-81 "Bearing and enclosing structures".

2.21. Acceptance of the assembled fittings is carried out before the installation of the formwork and is drawn up by an act of inspection of hidden works. The acceptance certificate of the assembled reinforcement structures must indicate the numbers of the working drawings, deviations from the drawings, and the assessment of the quality of the assembled reinforcement.

After the installation of the formwork, they give permission for concreting.

2.22. Reinforcement work flow diagrams are shown in Fig. 6 and 7.

Concrete works

2.23. Before the start of placing the concrete mix, the following work must be performed:

the correctness of the installed fittings and formwork was checked;

all formwork defects were eliminated;


Foundation F-1 for reinforced concrete columns

Rice. 1

Layout scheme for formwork panels

Pos. see fig. 3.

Rice. 2


Specification of formwork elements

Name

Quantity per foundation F-1, pcs.

Shield area, m 2

Weight, kg

one shield

on the foundation F-1

on the foundation F-1

Mounting corner

Mounting corner

Tension hook

Screed lock

Bracket with deck and hinged ladder

1. For the layout of the formwork panels, see fig. 2.

2. Bracket pos. 20 is not shown conventionally.

Rice. 3

Pos. see fig. 3.

Rice. 4


Formwork production scheme

1 - automobile crane KS-35715; 2 - storage area; 3 - formwork panels; 4 - contractions; 5 - mounting corners; 6 - enlarged formwork panels; 7 - reinforcing cage; 8 - sling; 9 - concrete preparation

Rice. 5


Foundation reinforcement scheme F-1

Layout scheme for grids soles

Reinforcement mesh specification

Conditional brand

Quantity, pcs.

Weight, kg

one element

Rice. 6

Reinforcement work flow chart

1 - automobile crane KS-35715; 2 - storage area; 3 - foundation formwork; 4 - laid reinforcement mesh; 5 - installed reinforcing cage; 6 - sling; 7 - inventory board(manufactured locally); 8 - concrete cover anchor

Rice. 7

the presence of clamps was checked, providing the required thickness of the concrete cover;

all structures and their elements, access to which in order to check the correctness of installation after concreting are not possible, have been accepted according to the act;

formwork and fittings are free of debris, dirt and rust;

the operation of all mechanisms was checked, the serviceability of accessories and tools was checked.

2.24. Delivery of concrete mix to the facility is provided by the SB-92V-2 or SB-159B-2 concrete mixer trucks.

2.25. Concrete supply to the place of laying is considered in two versions:

a truck crane in swivel bins with a capacity of 1.6 m 3 of a mixture designed by AOZT TsNIIOMTP;

using a concrete pump.

2.26. The work on concreting foundations includes:

reception and supply of concrete mix;

laying and compacting concrete mix;

curing.

2.27. Foundations are concreted in two stages:

at the first stage, the foundation shoe and the sub-column are concreted to the mark of the bottom of the liner;

at the second stage, the upper part of the sub-column is concreted after the insert is installed.

2.28. For loading with concrete, the rotary bins do not require reloading racks, but are fed to the place of loading with concrete by an automobile crane, which sets the bins in a horizontal position.

A concrete mixer truck drives up to the hopper in reverse and unloads. Then the truck crane lifts the bucket and in a vertical position delivers it to the place of unloading. In the area of ​​operation of a truck crane, several bunkers are usually placed close to one another, with the expectation that their total capacity is equal to the capacity of a concrete mixer. In this case, all prepared bucket bins are loaded with concrete mixture at the same time and then the crane alternately delivers them to the unloading point.

2.29. When concreting monolithic foundations with a concrete pump, the radius of action of the distribution boom allows placing the concrete mixture in several foundations. Normal operation of concrete pumps is ensured if a concrete mixture with a mobility of 4 - 22 cm is pumped through a concrete pipeline, which contributes to the transportation of concrete over extreme distances without delamination and the formation of traffic jams.

2.30. Schemes for the production of concrete works are given in Fig. 8 and 9.

2.31. The concrete mix is ​​laid in horizontal layers 0.3 - 0.5 m thick.

Each layer of concrete is carefully compacted with deep vibrators. When compacting the concrete mixture, the end of the working part of the vibrator should be immersed in the previously laid layer of concrete by 5 - 10 cm. The step of repositioning the vibrator should not exceed 1.5 of its radius of action. In the corners and at the walls of the formwork, the concrete mixture is additionally compacted with vibrators or bayonet with manual shurovki. Touching the vibrator during operation to the valve is not allowed. Vibration at one position ends when the sedimentation and the appearance of cement laitance on the concrete surface stops. When rearranging, the vibrator should be removed slowly, without turning it off, so that the void under the tip is evenly filled with the concrete mixture.

The break between the stages of concreting (or laying layers of concrete mixture) should be at least 40 minutes, but not more than 2 hours.

2.32. After placing the concrete mixture in the formwork, it is necessary to create favorable temperature and humidity conditions for concrete hardening. The horizontal surfaces of the concrete foundation are covered with damp burlap, tarpaulin, sawdust, sheet, roll materials for a period depending on climatic conditions, in accordance with the instructions of the construction laboratory.

2.33. Work on the construction of monolithic concrete foundations is performed by the following links:

unloading and sorting of reinforcing meshes and formwork elements, loading and unloading reinforcement cages assembled at the stand, installation of reinforcement cages for column columns, installation and dismantling of liners - link No. 1:

machinist 5 bits - 1 person,

assembler (rigger) 4 bit - 1 person,

2 bit - 2 people.

formwork - installation of formwork elements for foundations, disassembly of the formwork with surface cleaning, lubrication of panels with emulsion - link No. 2:

construction locksmiths 4 razr. - 2 people,

3 bit - 1 person,

2 bit - 1 person;


Scheme of the production of concrete works when feeding concrete mixture by crane in bunkers

1 - automobile crane KS-35715; 2 - concrete mixer truck SB-92V-2; 3 - rotary bunker BPV-1.6; 4 - sling; 5 - bracket; 6 - fencing; 7 - formwork panels; 8 - concrete foundation; 9 - storage area

Rice. eight

Scheme of the production of concrete works when feeding concrete mixture by a concrete pump

1 - concrete pump SB-170-1; 2 - concrete mixer truck SB-92V-2; 3 - formwork panels; 4 - concrete foundation

Rice. nine


reinforcement work - installation of reinforcing mesh for shoes, enlarging assembly of reinforcement mesh for support columns on the conductor, welding works - link No. 3:

fitters 3 razr. - 1 person,

2 bit - 2 people,

electric welder 3 bit - 1 person;

concrete work (when feeding the concrete mixture by a crane) - receiving the concrete mixture from a concrete mixer, feeding the concrete mixture with a crane, laying the concrete mixture with compaction with vibrators, taking care of concrete - link No. 4:

concrete workers 4 dig. - 1 person,

3 bit - 1 person,

2 bit - 2 people;

concrete work (when feeding the concrete mixture by a concrete pump) - laying the concrete mixture with a concrete pump with compaction with vibrators, cleaning the concrete pipeline, taking care of concrete - link No. 5:

machinist 5 bits - 1 person;

operator 5 bit - 1 person,

concrete workers 3 razr. - 1 person,

2 bit - 1 person.

2.34. Concrete work at negative air temperatures.

When carrying out concrete work in winter, one should be guided by the rules of SNiP 3.03.01-87 "Bearing and enclosing structures" and SNiP III-4-80 * "Safety in construction".

Winter concreting conditions are considered when the average daily outside air temperature is not higher than 5 ° С or minimum temperature during the day below 0 ° С.

In winter conditions, the choice of additives and the calculation of their amount is carried out in the same way as in the summer.

The erection of monolithic reinforced concrete structures can be carried out, as a rule, using several methods of winter concreting. The choice of the method should be made based on the requirements of the minimum values ​​of labor intensity and energy consumption, cost and duration of work, as well as taking into account local conditions (outside air temperature, scope of work, availability of special equipment, electrical power, etc.).

Combined methods of winter concreting are promising, which are a combination of two or more traditional methods, for example, a thermos + the use of concretes with antifreeze additives, electric heating or heating in the heating formwork of concretes containing antifreeze additives, electrical treatment of concrete in hot houses, etc.

Thermos way

The essence of the method consists in heating concrete by heating aggregates and water and using the heat released during cement hardening to acquire a given strength by concrete during its slow cooling in a heat-insulated formwork.

Application of concrete with anti-freeze additives

The essence of the method lies in the introduction into the concrete mixture during its preparation of additives that lower the freezing point of water, ensuring the reaction of cement hydration and concrete hardening at temperatures below 0 ° C.

Additives are introduced into the concrete mixture in the form of aqueous solutions of working concentration, which are obtained by mixing concentrated solutions of additives with mixing water and fed into the concrete mixer through a water dispenser.

Preliminary electric heating of concrete mix

The essence of the method lies in the rapid heating of the concrete mixture outside the formwork by passing an electric current through it, placing the mixture in the insulated formwork, while the concrete reaches the specified strength during the slow cooling process.

Preliminary electric heating of the concrete mixture is carried out in the bodies of dump trucks using the post equipment for heating the mixture.

When delivering the concrete mix by concrete mixers, the mix is ​​preheated at the heating station, followed by loading the mixer with the heated mix.

To avoid excessive thickening of the combustible concrete mixture, the duration of its warming up should not exceed 15 minutes, and the duration of transportation and laying - 20 minutes.

An exoteric method can be used to preheat the concrete mixture. When mixing the mixture with aluminum powder, an exothermic (with the release of heat) reaction occurs.

Electric heating of concrete

The essence of electric heating of concrete consists in passing through it, as through an ohmic resistance, alternating current, as a result of which heat is released in the concrete.

Steel electrodes are used to supply voltage to concrete.

For power supply of electric heating and other methods of electric heat treatment, it is allowed, as a rule, to use step-down transformers.

Heating of concrete in thermoactive formwork

The heating method is advisable when using inventory formwork with a steel or plywood deck when concreting walls, ceilings, etc.

It is especially effective in the construction of structures and structures, the concreting of which should be carried out without interruption, as well as structures saturated with reinforcement. The heating method is economically and technologically expedient not only when using collapsible and movable, but also block, volumetric-movable, rolling and sliding formworks.

The use of thermoactive formwork does not cause additional requirements for the composition of the concrete mixture and does not limit the use of plasticizing additives. Heating of concrete in a heating formwork can be combined with electric heating of a concrete mixture, using antifreeze chemical additives or hardening accelerators.

Heating of concrete structures is carried out after the formwork for concreting. Those parts of the structure that are not covered with thermoactive formwork are insulated with flexible coverings (blankets) made of fiberglass and glass wool.

The technology of concreting in thermoactive formwork practically does not differ from the technology of work in the summer. To prevent heat losses from horizontal surfaces during breaks in the laying of concrete mixture and the outside air temperature is below minus 20 ° C, the structure to be concreted is covered with a tarpaulin or film material.

Heating of concrete using heating wires

The essence of the concrete heating method using heating wires is to heat concrete using wires in the concrete, which are heated when an electric current is passed. The wires are fixed to the reinforcing bars of the meshes and frames before the concrete is placed.

Heating concrete with hot air

The use of hot air for heating concrete leads to large heat losses. Therefore, this method is advisable to use at a low negative outside temperature and sufficiently reliable and hermetically sealed thermal insulation. Hot air is obtained in electric heaters or fired heaters operating on liquid fuel.

2.35. The list of machines and equipment is given in table 1.

2.36. The list of technological equipment, tools, inventory and fixtures is given in Table 2.

List of machines and equipment

Table 1

Name of machines, mechanisms and equipment

Type, brand

Technical specifications

Appointment

Automobile crane

Telescopic boom length 8 - 18 m. Lifting capacity 16 t

Supply of reinforcement, formwork, concrete mix

Concrete pump

SB-170-1 (SB-170-1A)

Distribution boom delivery range - 19 m. Productivity up to 65 m 3 / h

Concrete supply

Concrete mixer truck

The geometric volume of the drum is 6.1 m 3. The output of the finished mixture is not less than 4.5 m 3

Concrete transport

Welding transformer

Supply voltage 200/380 V. Rated power 32 kW. Weight 210 kg

Welding works

Compressor

Compressed air supply

List of technological equipment, tools, inventory and fixtures

table 2

Name of equipment, tools, inventory and fixtures

Brand, GOST, TU or development organization, working drawing number

Technical specifications

Appointment

Number per link (brigade), pcs.

Rotary bunker

Capacity 1.6 m 3

Concrete supply

Paint heating tank

Capacity - 20 l, weight - 20 kg

Lubrication of formwork panels

Manual pneumatic paint sprayer

Weight - 0.66 kg

Lubrication of formwork panels

Rebar tying device

Orgtekhstroy

Assembly of prefabricated frames

Clamp for temporary fastening of reinforcement meshes

AOZT TsNIIOMTP

Reinforcement work

Latch for temporary fastening of reinforcing cages

Mosorgpromstroy

Reinforcement work

Constructor for the assembly of reinforcing cages

Giproorgselstroy

Reinforcement work

Twist

Reinforcement work

Drill universal

Drill diameter up to 13 mm, weight 2 kg

Drilling holes

Electric holder

Welding works

Deep vibrator

Vibrotip length 440 mm, weight 15 kg

Concrete compaction

Sling six-branch universal

AOZT TsNIIOMTP R. Ch. 907-300.000

Slinging structures

Assembly scrap

Weight 4.4 kg

Straightening elements

Chisel

Weight 0.2 kg

Cleaning of welding spots

Bench hammer

Weight 0.8 kg

Cleaning of welding spots

Steel construction hammer

Weight 2.2 kg

Tapping concrete

Weight 0.34 kg

Leveling mortar

Blacksmith's sledgehammer blunt-nosed

Weight 4.5 kg

Bending reinforcing bars

Mortar shovel

Weight 2.04 kg

Solution supply

Metal brush

TU 494-61-04-76

Weight 0.26 kg

Cleaning reinforcement from rust

Metal scraper

Weight 2.1 kg

Cleaning the formwork from concrete

Spanners

Formwork works

1 set

Rebar shears

Weight 2.95 kg

Reinforcement work

Combination pliers

Weight 0.2 kg

Reinforcement work

End pliers

Weight 0.22 kg

Reinforcement work

File

Weight 1.33 kg

Reinforcement work

Measuring tape

Steel construction plumb bob

Weight 0.425 kg

Control and measuring works

Construction level

Weight 0.4 kg

Control and measuring works

Safety glasses

Weight 0.07 kg

Safety engineering

Protective shield for electric welder

Weight 0.48 kg

Safety engineering

Construction helmet

Safety engineering

All link

Safety belt

Safety engineering

All link

Rubber gloves

Concrete works

Rubber boots

Concrete works

3. REQUIREMENTS FOR QUALITY AND ACCEPTANCE OF WORKS

3.1. Requirements for the quality of supplied materials and products, operational control quality and technological processes subject to control are shown in Table 3.

Table 3

The name of the technological processes to be controlled

Subject of control

Control method and tool

Control time

Responsible for control

Quality assessment specifications

Reinforcement acceptance

Compliance of reinforcing bars and meshes to the project (according to the passport)

Visually

Before installation

Work Producer

Diameter and distance between working rods

Vernier caliper, measuring ruler

Before installing the meshes

Installation of fittings

Deviation from the design dimensions of the cover thickness

Measuring ruler

In progress

Permissible deviation with a protective layer thickness of more than 15 mm - 5 mm; with a protective layer thickness of 15 mm or less - 3 mm

Displacement of reinforcing bars when they are installed in the formwork, as well as during the manufacture of reinforcing cages and meshes

Measuring ruler

In progress

The permissible deviation should not exceed 1/5 largest diameter rod and 1/4 of the rod to be installed

Deviation from the design dimensions of the position of the axes of vertical frames

Geodetic instrument

In progress

Tolerance 5 mm

Formwork acceptance and sorting

The presence of sets of formwork elements. Element marking

Visually

In progress

Work Producer

Formwork installation

Displacement of the axes of the formwork from the design position

Measuring ruler

During installation

Tolerance 15 mm

Deviation of the formwork plane from the vertical for the entire height of the foundation

Plumb line, measuring ruler

During installation

Tolerance 20 mm

Laying concrete mix

Concrete layer thickness

Visually

In progress

The layer thickness should be no more than 1.25 times the length of the working part of the vibrator

Concrete compaction, concrete care

Visually

In progress

The step of repositioning the vibrator should not be more than 1.5 of the vibrator's radius of action, the immersion depth should be slightly greater than the thickness of the laid concrete layer. Favorable temperature and humidity conditions for concrete hardening should be ensured by protecting it from the effects of wind, direct sunlight and systematic moistening

Concrete mix mobility

Konus Stroy - TsNIL-press (PSU-500)

Before concreting

Construction laboratory

The mobility of the concrete mixture should be 1 - 3 cm of the cone settlement according to SNiP 3.03.01-87

The composition of the concrete mixture when laying with a concrete pump

Experienced pumping

Before concreting

Construction laboratory

Experimental pumping of concrete mix by a truck-mounted concrete pump and testing of concrete samples, production of concrete mix samples from waste after pumping

Structural stripping

Verification of adherence to the demoulding deadlines, no damage to the concrete during demolding

Visually

After the concrete has been cured

Work foreman, construction laboratory

4. CALCULATION OF LABOR COSTS AND MACHINE TIME

Table 4

Name of technological processes

Unit measurements

Scope of work

Justification (ENiR and other norms)

Time norms

Labor costs

workers, man-h

drivers, man-h

workers, man-h (machine-h)

drivers, man-h (machine-h)

Installation and dismantling of formwork

Ancillary work

Unloading the formwork elements with Vehicle

ENiR 1987

§ E1-5 tab. 2 No. 1a, b

Sorting structures

ENiR 1987

§ E5-1-1 No. 3

Joint assembly of panels

ENiR 1987

§ E4-1-40 No. 1

Formwork installation

Supply of enlarged panels to the installation site

ENiR 1987

§ E1-6 tab. 2 No. 17а, b

Installation of enlarged panels

ENiR 1987

§ E4-1-37 tab. 2 No. 1 K = 0.9 (applicable)

Installing Scaffolding Brackets

ENiR 1987

§ E5-1-2 No. 4

Dismantling the formwork

Dismantling of enlarged formwork panels

ENiR 1987

§ E4-1-37 tab. 2K = 9 (applicable)

Removing the bracket

ENiR 1987

§ E5-1-2 No. 4 K = 8 (PR-2)

Supply of enlarged panels to the storage area

ENiR 1987

§ E1-6 No. 17a, b

Fitting installation

Unloading reinforcement meshes and cages

ENiR 1987

§ E1-5 tab. 2, no. 1a, b

Sorting reinforcement meshes:

ENiR 1987

§ E5-1-1 No. 3

ENiR 1987

§ E5-1-1 No. 3

Crane feeding to the place of installation

ENiR 1987

§ E1-6 tab. 2, No. 17а, b

Installation of shoe mesh reinforcement:

ENiR 1987

§ E4-1-44 tab. 1, no. 1 a

ENiR 1987

§ E4-1-44 tab. 1, no. 1a

Pre-assembly of reinforcement cages at the pre-assembly site

1 element / t

ENiR 1987

§ E5-1-3 table. 2, No. 1k, 2k

Loading of reinforcing cages on vehicles

ENiR 1987

§ E1-5, tab. 2, no. 1a, b

Crane supply of reinforcement cages to the installation site

ENiR 1987

§ E1-6, tab. 2, No. 17а, b

Installation of reinforcement cages by crane

ENiR 1987

§ E4-1-44 tab. 1, no. 2a

Rebar welding

ENiR 1987

§ E22-1-1 No. 26 K = 1.3 (B2-5)

Concrete works

Concrete supply by crane

Receiving concrete mix from a concrete mixer into bunkers

Delivery of concrete mixture to the place of laying in bunkers by crane

ENiR 1987

§ E1-6 tab. 2, No. 15, 16 (by extrapolation)

ENiR 1987

§ E4-1-49 table. 1, no. 4

Concrete delivery by a concrete pump

Receiving concrete mix from a concrete mixer into the bunker of a concrete pump

Concrete supply to the place of laying by a concrete pump

Placement of concrete mix in a structure with a volume of up to 25 m 3

ENiR 1987

§ E4-1-49 table. 1, no. 3, 4

Total when feeding concrete mix:

by concrete pump


5. SCHEDULE OF WORK PRODUCTION

Table 5


6. NEED FOR MATERIALS, PRODUCTS AND STRUCTURES

6.1. The need for materials, products and structures for the foundation is shown in Table 6.

Table 6

Name of materials, products and structures (brand, GOST, TU)

Unit measurements

Initial data

The need for a meter of the final product

Main developments

Unit standard measurements

Scope of work in standard units

Consumption rate

Small-panel metal formwork

Reinforcement mesh

Concrete mix

SNiP IV-B4 § E2

Electrodes Э-42

Emulsion for lubricating formwork panels

1 m 2 formwork

7. SAFETY AND LABOR PROTECTION. ENVIRONMENTAL AND FIRE SAFETY

7.1. When installing monolithic foundations, it is necessary to comply with the requirements of SNiP III-4-80 * "Safety in construction", "Fire safety rules during construction and installation work", "Rules for the design and safe operation of cranes".

7.2. The safety of work must be ensured: by choosing a rational and appropriate technological equipment;

preparation and organization of workplaces for the production of work;

the use of protective equipment for workers;

medical examination of persons admitted to work;

timely training and verification of the knowledge of working personnel and engineering and technical personnel on safety in the production of construction and installation works.

Pay particular attention to the following:

methods of slinging structural elements should ensure their supply to the installation site in a position close to the design one;

elements of the structures to be mounted during movement must be kept from swaying and rotating by flexible braces;

do not allow people to be found under the mounted structural elements until they are installed in the design position and secured;

when moving cargo by a crane, the distance between the outer dimensions of the carried cargo and protruding parts of structures and obstacles along the movement should be at least 1 m horizontally, and at least 0.5 m vertically; erection and dismantling of the formwork can be started with the permission of the technical manager of the construction and must be carried out under the direct supervision of a specially appointed person of the technical personnel;

moving a loaded or empty bunker is allowed only when the gate is closed;

the vibrator is not allowed to touch the armature and the worker is not in the area of ​​a possible fall of the bunker;

only persons who have a certificate for the right to work on this type of machine are allowed to operate concrete pumps.

7.4. When working at a height of more than 1.5 m, all workers must use safety harnesses with carabiners.

7.5. Dismantling of the formwork is allowed after the concrete has gained stripping strength and with the permission of the work manufacturer.

7.6. The separation of the formwork from the concrete is carried out using jacks. The concrete surface should not be damaged during the tearing off process.

7.7. Workplaces of electric welders should be fenced off with special portable fences. Before starting welding, it is necessary to check the serviceability of the insulation of the welding wires and electrode holders, as well as the tightness of the connection of all contacts. During interruptions in operation, electrowelding installations must be disconnected from the mains.

7.8. Loading and unloading operations, storage and installation of reinforcing cages should be carried out with inventory lifting devices and in compliance with measures to exclude the possibility of falling, sliding and loss of stability of goods.

7.9. Cleaning the tray of the concrete mixer and the loading opening from the remnants of the concrete mixture is carried out only with a stationary drum.

7.10. It is forbidden: to work the concrete pump without outriggers; to start the work of the concrete pump without first pouring water into the washing tank of concrete transport cylinders, and into the concrete pipeline - "starting lubricant".

8. TECHNICAL AND ECONOMIC INDICATORS

Table 7

Name

Delivery of concrete mix by crane in bunkers

Concrete supply by the concrete pump SB-170-1

Standard labor costs of workers, man-day

Standard costs of machine time, machine-shifts

Duration of work, shifts

Production per worker per shift, m 3 / person-shift

Calculation 1

Standards of time for unloading the concrete mixer SB-92V-2 in a container.

Unloading time of the concrete mixer by technical characteristics a concrete mixer truck is 8 minutes (0133 h).

Useful drum capacity - 4 m 3.

N. vr. for unloading 100 m 3 of concrete mixture will be:

(100´0.133) / 4´1 = 3.32 machine-hours

Calculation 2

Standards of time for the supply of concrete mixture to the structure by the concrete pump SB-170-1.

The operational performance of the concrete pump is determined by the formula

P e = P t ´ K 1 ´ K 2,

where P t is the technical performance of the concrete pump;

K 1 - coefficient of transition from technical performance to operational, K 1 = 0.4;

K 2 - coefficient of decrease in the productivity of the concrete pump, taking into account the non-constant supply mode, K 2 = 0.65.

P e = 60 ´ 0.4 ´ 0.65 = 15.6 m 3 / h.

Serves a link of two people: the driver of the concrete pumping unit 4 bits. - 1 person, concrete worker 2 dig. - 1 person

Time rate per 100 m 3 of concrete mix for workers:

(100´1) / 15.6 = 6.4 man-hours;

for the driver 100 / 15.6´1 = 6.4 machine-hours.